Live Demo — Diriyah Heritage Hotel & Residences
PRJ-KSA · Fictional training project · Riyadh · FIDIC Red Book · SAR 412M
Follow the project, not a list of screens
Start with the brief, then follow design → schedule → procurement → site work → commercial & finance → FF&E → handover. Each mission opens the working screen with instructions telling you what to click, what evidence to inspect and why it matters to the next stage.
Inspect existing records without creating orders, approving work or posting money. Missing data is a demonstration limitation, not proof that the project is complete. Mission progress tracks where you are learning, not project completion.
Project setup
Sep 2025 · Lead: Project DirectorProject gate (not certified by the demo): Project charter, budget, risks, roles and approvals set
Step 1 · Project charter & setup
Every drawing, order and payment must belong to the same project.
- Confirm PRJ-KSA (Diriyah Heritage Hotel) is shown in the top bar.
- Open AI Actions in the module header. Inspect source evidence; optionally select Run Analysis to generate a paid, read-only lifecycle audit and compare cited records. Do not confirm a follow-up task in this training project. Blueprint & Rules preserves broader proposed capabilities.
- Open Project setup in the lifecycle and read Project details: location, contract (FIDIC Red Book), currency SAR and key dates.
- Open an existing task with Details. Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can state the project, contract type, currency and dates.
Next handoff: These parameters bound the management plan and budget.
Step 2 · Project Management Plan
The plan explains how scope, time, cost, quality, risk and stakeholders will be managed.
- Scroll through the twelve management-area cards.
- Click one area (e.g. Schedule or Cost) and read the live evidence behind it.
- Note areas showing missing evidence; this dashboard is not a signed-off PMP.
Before continuing: You can name the twelve areas and spot one with weak evidence.
Next handoff: The cost area depends on an allocated budget.
Step 3 · Baseline budget by cost code
The budget is the cost limit; commitments and invoices are measured against it.
- Choose PRJ-KSA in Financial reporting scope and SAR as Statement currency.
- Review Profit & Loss from posted entries; use Project budgets & ledger for planned, committed and actual amounts.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can explain budget vs commitment vs actual cost.
Next handoff: Budget authority requires defined roles.
Step 4 · Roles & permission matrix
Each person may only do what their role allows.
- Review the role list: Project Director, QS, Planner, Resident Engineer, QA/QC, HSE, Procurement, Finance and others.
- Pick one role and read which modules it can view, edit and approve.
- Do not change the matrix in this walkthrough.
Before continuing: You can say which role certifies payments and which posts to the ledger.
Next handoff: Roles drive who receives approval requests.
Step 5 · Approval routing
Requests move between contractor, consultant and client in a fixed order.
- Open My Approvals and review any pending items.
- Open one item and read who raised it, who must approve and the amount/threshold.
- Do not approve or reject.
Before continuing: You understand how an item reaches the right approver.
Next handoff: Governance is completed by identifying project risks.
Step 6 · Project risk register
Risks such as heritage ground conditions, heat, lead times and FX must be owned early.
- Open the risk register filtered to PRJ-KSA.
- Open one risk and read probability, impact, owner, mitigation, the schedule activity at risk and its impact days.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can name a top risk and its mitigation owner.
Next handoff: With governance set, design and documents begin.
Design & Documents
Oct 2025 – Mar 2026 · Lead: Design ManagerProject gate (not certified by the demo): IFC drawings issued, submittals stamped, DGDA & Balady approvals
Step 7 · Location hierarchy
Drawings, defects and FF&E attach to a site → building → level → room tree.
- Expand the tree from site to levels and rooms.
- Select a guest room and note its code.
- Do not drag or reparent locations.
Before continuing: You can find a specific room in the tree.
Next handoff: Controlled documents reference these locations.
Step 8 · Controlled document environment (CDE)
Construction and quantities must refer to an identifiable drawing revision.
- Choose Drawing register and read a sheet's number, title, revision and status.
- Choose Files & links; a register row without an original is not a PDF.
- Choose Submittal stamps and Transmittals to see approval evidence. Do not stamp or issue.
Before continuing: You can name a drawing, its revision and whether an original exists.
Next handoff: Sheets are managed and compared in Drawing Sets.
Step 9 · Drawing sets & revision compare
Revisions must be compared before work proceeds on the new issue.
- Open a sheet with more than one revision (e.g. Rev A and Rev B).
- Use revision compare and view any pinned RFIs.
- Do not upload or delete sheets.
Before continuing: You can describe what changed between two revisions.
Next handoff: The current revision supplies quantities for takeoff.
Step 10 · Quantity takeoff
Quantities measured from calibrated drawings feed the estimate.
- Select a drawing and confirm the calibration scale is set.
- Review existing length, area, volume (m³) and count measurements.
- Do not add or delete measurements.
Before continuing: You can read a measured quantity and its unit.
Next handoff: 3D models are checked for clashes before pricing.
Step 11 · BIM coordination & clashes
Clashes found in the model are cheaper than clashes found on site.
- In 3D Viewer choose Load sample IFC model: three training elements, not the KSA design model.
- Run Clash Detection and inspect the intentional beam–duct intersection in Clash Matrix.
- Checks use imported mesh triangles, containment and clearance. Do not create an RFI from this training fixture; real imports are session-only.
Before continuing: You can identify a clash and the disciplines involved.
Next handoff: Verified scope is priced in the estimate.
Step 12 · Detailed cost estimate
An estimate turns scope into quantities, rates and a proposed cost.
- Open a saved PRJ-KSA estimate and note its status.
- Review lines, quantities, units and totals; open Build-up & quotes on one line.
- Open Revision history. Approved estimates are locked — do not re-baseline.
Before continuing: You can explain one line's quantity × rate.
Next handoff: Rates are benchmarked against history.
Step 13 · Historical rate benchmarks
Rates should be compared with past estimates, quotes and orders.
- In an estimate line's build-up, open the historical rate lookup.
- Compare same-unit, same-currency benchmarks and their sources.
- Do not adopt a rate in the demo.
Before continuing: You can say whether a rate is above or below history.
Next handoff: Approved scope is reviewed by stakeholders.
Step 14 · Stakeholder register & reviews
Contractor, consultant and client each have distinct authority.
- Switch between Classic Register and Executive Cockpit.
- Click a summary card to filter records; open one record's history.
- Do not raise or transition submittals.
Before continuing: You can say which party acts next on a record.
Next handoff: Approved design allows planning to start.
Scheduling
Sep 2025 – ongoing · Lead: Planner / SchedulerProject gate (not certified by the demo): Baseline approved, data date set, delays analysed
Step 15 · Schedule WBS
Work is broken into packages before activities are planned.
- Choose Activities & Gantt and confirm PRJ-KSA.
- Expand WBS sections from foundations through fit-out.
- Do not add WBS nodes.
Before continuing: You can name the main WBS sections.
Next handoff: Each WBS section holds CPM activities.
Step 16 · Activities, logic & interactive Gantt
The schedule shows what happens first and what drives completion.
- Click an activity row or Gantt bar to open its inspector.
- Read dates, duration, progress and predecessors/successors.
- Click Critical to trace the critical path. Do not resize bars.
Before continuing: You can name an activity's predecessor and whether it is critical.
Next handoff: Durations depend on working calendars.
Step 17 · Calendars & working time
6-day civil weeks, 24h pours and Ramadan shifts change real dates.
- Review the calendars list and their work weeks/holidays.
- See which calendar a trade activity uses.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can explain why two activities with equal duration finish on different dates.
Next handoff: Calendars and crews determine resource feasibility.
Step 18 · Resources & leveling
A plan is not credible if crews exceed what is available.
- Choose Links, resources & cost and inspect an activity's resource assignments.
- Choose Resources & leveling; review histograms and limits.
- Preview only — do not apply leveling.
Before continuing: You can spot a period where demand exceeds a limit.
Next handoff: The feasible plan is frozen as a baseline.
Step 19 · Look-ahead & risk warnings
Open risks can delay the next few weeks of work; the look-ahead shows which activities they threaten.
- Choose Look-ahead and set the window to 6 weeks.
- Read Risk warnings: 'Exceeds float' means the risk's delay is larger than the activity's spare time (or it is critical).
- Compare KSA-R04 (Saudization, +14 d on critical MEP rough-in K5010 — exceeds float) with KSA-R03 (chillers, +28 d on K2010 — within float) and open it in Risk & Compliance to see its owner and mitigation.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can name which look-ahead activity a risk threatens and whether float absorbs it.
Next handoff: Approved baselines measure delays formally.
Step 20 · Baselines & delay analysis (TIA)
Delays are measured against an approved baseline.
- Open Baselines and compare baseline vs current dates.
- Review recorded delay events / fragnets.
- Do not approve baselines or run TIA.
Before continuing: You can say how many days an activity has slipped.
Next handoff: Progress is measured with earned value.
Step 21 · Earned value & risk
Earned value shows whether work done matches money spent.
- Review SPI/CPI and the S-curve.
- Read any input warnings — zero budgets are not good performance.
- Review the Monte Carlo finish-date range.
Before continuing: You can explain SPI below 1.0.
Next handoff: Schedules are exchanged with Primavera via XER.
Step 22 · Projects tab: schedule import/export
Owners often require native P6 files.
- Open the Projects tab in Enterprise Scheduler.
- Find PRJ-KSA under its EPS and read Last imported / Last exported.
- Click Files & history to see staged files; do not import into PRJ-KSA.
- Open Schedule Analysis & Controls → Delay Analysis & TIA to read delay events.
Before continuing: You know how the schedule leaves and enters the platform.
Next handoff: Schedule dates set procurement need-by dates.
Procurement
Feb – Jun 2026 · Lead: Commercial / Procurement LeadProject gate (not certified by the demo): Packages awarded, POs issued, COI on file
Step 23 · Material requisitions
Site needs are requested against budget before buying.
- Open an existing requisition and read items, required-on-site date and budget line.
- Check its status and linked order if any.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can trace a requisition to its budget line.
Next handoff: Requisitions are packaged into RFQs.
Step 24 · Request for quotations
A request defines the package before suppliers price it.
- Choose an existing PRJ-KSA RFQ from the selector (do not create one).
- Read scope, invited vendors and recorded bids.
- Do not award, issue a PO or record payment.
Before continuing: You can identify the RFQ and its competing suppliers.
Next handoff: Bids are compared side by side.
Step 25 · Bid leveling
Recorded offers must be compared on the same commercial basis before award.
- Confirm PRJ-KSA and select a recorded RFQ package; no offers means no quotations recorded, not a sample recommendation.
- Compare quoted amounts, currency, lead days and notes/exclusions; adjust comparison weights only. Missing weighted reliability or ESG prevents ranking.
- Review / award in workflow opens the same RFQ. Inspect only — do not award.
Before continuing: You can explain which actual offer scores highest, or why inputs are insufficient.
Next handoff: Authorized procurement reviews the offer before issuing its purchase order.
Step 26 · Purchase orders
The purchase order is the agreed scope, price and destination.
- In Purchase orders, click an existing PRJ-KSA order (these are live project records).
- Read supplier, status, currency, amount, delivery destination and source RFQ.
- Read Goods receipts & invoices: without a receipt the invoice is not matched as delivered.
- Use "Open the full RFQ → PO → receipt → payment chain" to see the same order in the RFQ workflow. Do not award or pay.
Before continuing: You can distinguish order, delivery evidence and invoice.
Next handoff: Major trades use subcontracts.
Step 27 · Subcontracts & retention terms
Subcontracts carry retention, advance and defect terms.
- Open a KSA subcontract.
- Read scope by cost code, retention % and advance terms.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can state a subcontract's retention rate.
Next handoff: Contracted vendors need valid insurance.
Step 28 · Vendors & insurance (COI)
Expired insurance or registration blocks payment and site access.
- Open a vendor record.
- Check insurance certificates and expiry dates.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can say whether a vendor is compliant today.
Next handoff: Vendors work through their portal.
Step 29 · Vendor portal
Suppliers see only their own bids, orders and invoices.
- Review the portal layout: invitations, orders, deliveries, invoices.
- Note that a vendor account never sees other vendors' data.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You understand what a supplier can and cannot see.
Next handoff: Materials are ordered; site work begins.
Construction Site
Dec 2025 – Feb 2027 · Lead: Construction ManagerProject gate (not certified by the demo): RFIs answered, inspections signed, NCRs and safety closed
Step 30 · RFIs
An RFI records a design question and its answer.
- Choose RFIs and open an existing KSA record.
- Read subject, drawing reference, responsible party, status and response.
- Close without saving.
Before continuing: You can say who must answer and whether it is closed.
Next handoff: Clarified design leads to technical submittals.
Step 31 · Submittals & shop drawings
Materials must be approved before installation.
- Choose Submittals and open a record.
- Read the review status (Approved / Revise & resubmit).
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can distinguish a submittal from an RFI.
Next handoff: Daily reports record the work actually done.
Step 32 · Daily progress reports
Site progress feeds the schedule; it does not create payment entitlement.
- Choose Daily Progress & Quantities and open an existing report.
- Read activity, date, quantity, crew and photo evidence.
- Do not submit or approve reports.
Before continuing: You know why billing needs separate verified measurements.
Next handoff: Labor and equipment are recorded by cost code.
Step 33 · Labor, equipment & timecards
Crew hours by cost code show productivity and cost.
- Review labor and equipment entries for PRJ-KSA.
- Compare person-hours to the related activity.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can read person-hours for a crew.
Next handoff: Work is inspected at hold points.
Step 34 · Inspections & hold points
Some work cannot proceed until witnessed (e.g. rebar before pour).
- Open an inspection/ITP record.
- Read hold/witness points and sign-off status.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can say which hold point is pending.
Next handoff: Failures become NCRs.
Step 35 · NCRs & transmittals
Defective work needs root cause, correction and closeout.
- Open an NCR and read severity, cause and corrective action.
- Check its closeout status.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can explain what closes an NCR.
Next handoff: Quality goes with safety.
Step 36 · Safety & incident log
Incidents and rates (TRIR/DART) are tracked to zero harm.
- Review the incident log and rate indicators.
- Open one incident and read investigation details.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can read the current TRIR.
Next handoff: Site issues are coordinated in meetings.
Step 37 · Meetings & action items
Decisions and actions must be minuted and owned.
- Open a meeting and read attendees, minutes and actions.
- Check overdue actions.
- Do not finalize minutes.
Before continuing: You can name an action, owner and due date.
Next handoff: Site punch items are tracked to closure.
Step 38 · Punch list, weather & SLA
Snags must be closed before areas are handed over.
- Review the punch list by location and trade.
- Check weather log and response SLAs.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can find an open snag and its owner.
Next handoff: Completed work is valued commercially.
Finance (ERP)
Monthly · Lead: Finance ControllerProject gate (not certified by the demo): Changes agreed, pay apps certified, invoices matched and posted
Step 39 · Contract BOQ / SOV
Payment is based on the approved contract BOQ, not on site totals.
- Choose Contracts & SOV and open an item.
- Read rate, effective date and valuation rule (measured / lump sum / milestone).
- Open Revision history. Do not import or revise.
Before continuing: You can explain how one item is valued.
Next handoff: Quantities are verified by joint measurement.
Step 40 · Joint measurements
Contractor and consultant agree quantities before claiming.
- Choose Measurement and open a sheet.
- Compare previous, current and cumulative quantities and evidence.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can explain the current-period quantity.
Next handoff: Scope changes go through variations.
Step 41 · Variations
Changes follow event → reviewed proposal → authorized BOQ.
- Choose Variations and open a record.
- Follow its status and any schedule handoff.
- Do not authorize.
Before continuing: You can say whether a variation has entered the BOQ.
Next handoff: Measured and varied work is claimed in an IPC.
Step 42 · Payment applications (IPC)
Claim, certification, client approval and posting are separate decisions.
- Choose Payment Applications and open one.
- Read gross value, retention, advance recovery, VAT and net.
- Do not certify, authorize or post.
Before continuing: You can explain which approval comes before a receivable is posted.
Next handoff: Contracts are secured by guarantees.
Step 43 · Securities & guarantees
Performance bonds and advance guarantees must stay valid.
- Choose Securities & guarantees.
- Read value, bank, expiry and release condition; empty means none seeded.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can say when a guarantee expires.
Next handoff: Certified amounts and supplier invoices reach the ledger.
Step 44 · Payables, receivables & ledger
The ledger records approved transactions, not site progress.
- Review Payables and Receivables for PRJ-KSA in native currency.
- Open Ledger entries and compare debits and credits for one reference.
- Optional specialist-work handoff: Consultant Services has SOW, private originals, rate-capped hours and protected P6/BOQ drafts. Signed-off release posts one AP/professional-fees accrual; draft acceptance never overwrites baselines. Inspect only; do not fund, approve or release.
- Do not create invoices, payments or close periods.
Before continuing: You can distinguish AP, AR and journal posting.
Next handoff: Supplier invoices can be scanned.
Step 45 · Invoice scanning
Extraction speeds entry but must be checked against the order.
- Review a scanned invoice result.
- Compare extracted supplier, amount and VAT with the vendor record.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can spot an extraction mismatch.
Next handoff: Foreign-currency items need revaluation and e-invoicing.
Step 46 · FX & Saudi e-invoicing
USD/EUR balances are revalued to SAR; invoices follow ZATCA rules.
- Review revaluation rates and results.
- Open an e-invoice document record.
- Note that live ZATCA clearance needs credentials.
Before continuing: You can explain an FX revaluation gain or loss.
Next handoff: Cash flow and forecasts summarize the money.
Step 47 · Cash flow & forecasts
Forecasts show final cost and finish before they happen.
- Review cost and schedule forecasts for PRJ-KSA.
- Compare forecast at completion to budget.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can state forecast overrun or underrun.
Next handoff: With construction and finance understood, review the fit-out.
FF&E Fit-Out
Sep 2026 – May 2027 · Lead: FF&E / Interiors LeadProject gate (not certified by the demo): FF&E delivered, installed and every room released
Step 48 · FF&E workflow
Fit-out runs spec → budget → buy → ship → install → hand over.
- Review the six-phase pipeline and counts per phase.
- Click a phase to see its items.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can say which phase holds most items.
Next handoff: Every item starts from an approved spec.
Step 49 · FF&E specifications
Items must match approved finishes and ratings.
- Open a spec and read finish, manufacturer code and rating.
- Check whether an original spec sheet is attached.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can tell an approved spec from a draft.
Next handoff: Specs populate the room catalogue.
Step 50 · Room-by-room FF&E catalogue
Room quantities, specifications and finish evidence become the fit-out team's reviewed scope.
- Open an item and read room, quantity, cost and status; filter by room type.
- Scroll to FF&E Delivery Controls. Inspect Custody Pipeline, Finish Samples, Room Readiness and Item Originals.
- Select Client room presentation or Item tear sheets and download a presentation PDF. Review linked photos where available, then download originals ZIP and inspect its missing-evidence manifest. These review copies do not approve specifications.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can identify an item's room and its specification review package.
Next handoff: Civil/MEP release and recorded custody govern installation; registered assets feed handover.
Step 51 · Room matrix & heatmap
The heatmap shows which rooms are ready for installation.
- Review the floor-by-floor heatmap.
- Click a room cell to see missing items.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can find a room that is not ready.
Next handoff: Items arrive through shipments.
Step 52 · Shipments & warehouse
Imported items move port → customs → warehouse → site.
- Open a KSA shipment and read origin, ETA and customs status.
- Check goods receipt records.
- Review containers and demurrage risk on the containers screen if needed.
Before continuing: You can say where a shipment is now.
Next handoff: Delivered items are installed and rooms released.
Step 53 · Room release
Delivery is not completion; rooms pass five release stages.
- Open a room release record.
- Read the five stages and supporting evidence.
- Do not advance stages.
Before continuing: You can distinguish delivered, installed and accepted.
Next handoff: Accepted rooms feed handover.
Handover & GRC
Mar – Jun 2027 · Lead: Project Director / QAProject gate (not certified by the demo): COBie delivered, audits done, closeout checklist complete
Step 54 · Assets, COBie & commissioning
The operator needs traceable serialized assets, documents and warranties rather than procurement quantities alone.
- Choose Asset Register & COBie; inspect an asset and completeness issues.
- Export COBie draft workbook and review Facility, Space, Type, Component, Document, FFE_Items and Issues. Missing assets/dates stay explicit; no assets are created by export.
- Review Documents, Commissioning and Defects & Warranties. Owner template validation and original document mapping remain required; do not accept the project.
Before continuing: You can list the draft workbook's missing evidence and distinguish FF&E quantities from asset tags.
Next handoff: Authorized acceptance and resolved closeout evidence support retention release.
Step 55 · Retention release
Held retention is released only after defects and waivers.
- Review retention releases for a KSA subcontract.
- Read the release condition and status.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can say what must happen before release.
Next handoff: Compliance and audit close governance.
Step 56 · Compliance & audit trail
Every change and approval must be traceable.
- Review audit trail entries for PRJ-KSA.
- Review policies and third-party risk.
- Inspect only — do not create, approve or post anything in the demo project.
Before continuing: You can find who changed a record and when.
Next handoff: The project closes through the closeout gate.
Step 57 · Closeout gate
Learning can finish while the project still has open obligations.
- Open Handover & GRC in the Projects lifecycle.
- Review incomplete closeout items rather than ticking them.
- Click Finish demo. Do not archive PRJ-KSA.
Before continuing: You can explain what blocks real project closure.