Complete operations manual — organised by module, with comparison matrices, integration maps, and a premium branded PDF export.

OPERATIONS MANUAL · v3.64 · 2026-11-25

49 chapters · 323 steps

Project lifecycle manual — setup to handover

Follow this manual from project initiation to handover and financial closeout. Each chapter identifies the responsible person, the menu to open, the actions to take, and the evidence required before proceeding. Use your organization's approval rules and verify saved records after every important change.

Orientation→Start Here · Project setup→1 · Design & Documents→2 · Scheduling→3 · Procurement→4 · Construction Site→5 · Finance (ERP)→4 · Construction Site → 5 · Finance (ERP)→6 · FF&E Fit-Out→7 · Handover & GRC→Start Here→Reference · Platform hardening→Construction governance→6 · FF&E / 7 · GRC→1 · Design & Documents / 2 · Scheduling→Cross-module ownership→Reporting & sustainability→AI execution and discipline review→Evaluation and preferences→Administration & AI→Commercial & Finance — optional specialist services→FF&E Fit-Out — specification exchange and client sign-off→Procurement→Planning→Commercial, claims and technical review→Administration
01

Orientation

How the menu is organized

Responsible: All users

  1. 1

    Load demo projects into an empty workspace

    Sign in with Administrator access and choose Settings → Seed Demo Data, or the same action in All tools. Confirm to add PRJ-KSA (SAR), MTC-2 (AED) and PRJ-001 (USD) as clearly labeled fictional training projects. Each newly created project contains five WBS nodes, ten linked activities, a six-day work calendar, three labor resources, eight assignments, four planned budget categories and three lifecycle tasks. Project choices and open registers refresh after loading; choose a project in the top dropdown and open Enterprise Scheduler to see activities, Gantt and resource loading. Repeating the action skips existing project IDs entirely, preserving their names, schedules and edited data. Loading either completes together or rolls back on error. This button does not add FF&E items or all walkthrough evidence, issue purchases, post invoices, connect external services or restore a missing XER archive. FF&E demo items have their own existing Load demo data action. Clear All Data remains a legacy browser-only control and does not delete these database records.

  2. 2

    Workspace rail, project context and All tools

    Choose the working project from the project name in the top bar. The dark left rail groups the 25 everyday tools into five suites (Command & Workspace, Design & Planning, Site & Field Ops, Commercial & Supply, Governance & AI); every other permitted screen is under More tools. All tools opens the same suites as a searchable mega-menu. Pin tools on the ribbon with +; pins are saved per account in this browser and never grant access. Global Search still finds records and screens.

  3. 3

    Enterprise record review

    Construction and shared enterprise registers show actual status counts, search, ordered Columns and Export. Select a status or type text to filter; use the column gear to show, hide and reorder columns. Row checkboxes select loaded records across pages; Select all applies to the filtered set, and Export selected exports exactly those rows. Construction batch controls update only fields supported by the existing workflow: punch/WBS/QA status or assignment, and RFI/submittal assignment only, with explicit confirmation. Approval, issue and financial posting are never available as batch shortcuts. Each update goes through its existing save handler; a partial failure reports the completed count and stops. RFI/submittal workflow steppers are read-only status indicators, with recorded chronological activity and change details; no history is fabricated. Other module details retain the shared docked inspector. Classic Stakeholder Register remains available.

  4. 4

    Scheduling layouts, filters and bottom profile

    Open Enterprise Scheduler → Activities & Gantt. Choose Default, 3-Week Lookahead, Critical Path, Cost & Earned Value or Milestones. Critical path uses total float ≤ 0; Behind schedule compares recorded progress against planned progress at the data date. In progress excludes zero and completed work. Save the current columns, zoom, filter, baseline visibility and bottom-dock choice as a named layout; layouts are stored for your account and project in this browser and can be replaced or deleted. Baseline bars below current activities show only an existing approved baseline and can be toggled; no baseline is invented. The resizable bottom pane switches between the Detail inspector and Resource profile / S-Curve. Resource profile uses canonical assignments, displays weekly unit-day loading and planned costs; S-Curve plots baseline/current planned value and the actual recorded earned-value point at the data date, not fabricated earned-value or cost history. These are workspace conveniences, not complete Primavera parity.

  5. 5

    FF&E table, mood board, room matrix and client binder

    Open Fit-Out & FF&E Management and use Table grid, Mood board, Room matrix or Client room binder. All four show the same selected-project items and respect the room-type filter; choose a specific room with the Room selector. Mood board uses private signed product photos and original cut-sheet links, displaying an explicit missing-photo state when none exists. Selecting a card opens the existing item inspector. Room matrix groups all records by room and item name, sums specified, installed and ordered quantities, and opens the exact source rows from each cell. Client room binder hides internal net costs and margins and uses the existing freight/markup sell-price calculation; Download room binder PDF reuses the same canonical items/media and creates a client review copy. Client approvals remain in existing Client Links / Client Board workflows; viewing or exporting never changes procurement status. This does not include live Fohlio sync, plugins or certified e-signature.

  6. 6

    Partner Showcase: individual scripts and A–Z workflow

    Open Partner Showcase for the existing nine-act presentation. Select a named stop to see its distinct Say this explanation: what the screen does, why it matters in construction and how its evidence hands off to other modules. Start Autopilot opens the screens in sequence; optional AI voice reads that stop's full script in bounded clips and waits for completion. Pause resumes the current audio clip rather than repeating the phase script. Voice remains selectable and narration can be switched off for the presenter to speak. A–Z module workflow lists the delivery stages, modules, tabs and working sections with handoffs and evidence limitations. Autopilot does not submit forms, approve records or perform automatic operational clicks.

  7. 7

    Start Here

    Projects opens the selected company project as a working lifecycle dashboard. Project setup, Design & Documents, Scheduling, Procurement, Construction Site, Finance (ERP), FF&E Fit-Out and Handover & GRC each contain live source records and their own tasks. Setup opens first. Live Demo is separate PRJ-KSA training with 57 guided steps across those same eight stages.

  8. 8

    Stages 1 to 7 follow the project in order

    Start Here → 1 Design & Documents → 2 Scheduling → 3 Procurement → 4 Construction Site → 5 Finance (ERP) → 6 FF&E Fit-Out → 7 Handover & GRC.

  9. 9

    Scheduling is separate from site work

    Stage 2 holds the schedule (WBS, activities, calendars, baselines, delay analysis, XER). Stage 4 holds what happens on site (RFIs, submittals, daily logs, inspections, safety).

  10. 10

    FF&E is its own stage

    In the delivery walkthrough, complete construction/site management and commercial/finance before FF&E fit-out. FF&E is the final delivery stage before handover. Ordinary Projects always displays all eight working stages, including stage 6 FF&E; training walkthroughs still filter steps by project type.

  11. 11

    Every record opens

    Click any table row to see all its fields, move between records with the arrow keys and copy the details.

  12. 12

    Page through record lists

    Record tables offer Records per page with 10, 25, 50, 100, 250 or 500 records, plus first, previous, next and last page controls. Apply search and filters before paging; changing the matching records returns to the first page. Totals and exports continue to use the full source records. Enterprise Scheduler Activities and Enterprise activities use the same controls, with no first-500 display cutoff. EPS pages visible hierarchy nodes and projects together; expand or collapse nodes to change the visible list.

  13. 13

    Advanced tools

    Admin & Advanced holds permissions, module switches, integrations, offline/sync testing and the legacy scheduler.

  14. 14

    Walkthroughs use the same order

    Open Live Demo and choose Start guided demo. Sixteen missions explain the purpose, exact screen actions, evidence checkpoint and next business handoff from setup to closeout. The destination's single instruction guide remains visible with Previous mission, I've reviewed this · Next mission, Demo overview and Exit training. Instructions can be collapsed and reopened. Demo overview retains the current mission for Resume; refreshing a training destination retains its instructions and PRJ-KSA. Repeated destinations such as the scheduler have distinct missions. Ordinary navigation without training context restores the previously selected working project. Old walkthrough progress is rejected. Advancing acknowledges learning only: it does not approve work, change project stages, create orders or post finance.

  15. 15

    Open the protected Live Demo

    Start Here → Live Demo — KSA Project remains the learning entry point. The guided missions inspect canonical fictional PRJ-KSA records rather than create a parallel dataset. Use Begin mission to revisit a specific exercise or Start guided demo to follow the complete order. Missing originals, reports, securities or approval evidence are limitations to recognize, not invented completion. Instructions do not weaken any operational permissions or financial approval controls.

Done when

One sequence is visible and PRJ-KSA remains selected on demo screens.

Important: These are ordered learning steps, not automatic construction completion or approval gates. The KSA project contains fictional demonstration data.

02

Orientation

Project Management Plan (PMP) dashboard

Responsible: Project director

  1. 1

    What the PMP dashboard is

    PMP — Plan Dashboard (Start Here group) aggregates the selected project's live records into the twelve PMBOK knowledge areas. Every figure is read live from the operational modules at the project's data date — nothing is typed into the dashboard itself. It is read-only: each card has an Open module link that takes you to the screen where the underlying records are created and edited. Select the project from the top dropdown first; the dashboard follows that selection.

  2. 2

    Top health cards

    Four summary cards sit above the knowledge areas. Overall progress shows earned progress versus planned progress to the data date, computed from the schedule. Schedule performance (SPI) shows the schedule performance index at the data date with the count of critical and behind-plan activities. Cost: actual / budget shows actual cost as a percentage of the planned budget with committed value. Open risks / NCRs / RFIs shows the three open counts with high-residual-risk and overdue-approval callouts.

  3. 3

    Card 1 · Integration & Scope

    Owner: Project director. Shows the lifecycle stage, the number of WBS elements, the contract type and contract value, and the baseline start and finish dates. Use it to confirm the project is framed correctly before reviewing anything else. Open module: Projects.

  4. 4

    Card 2 · Schedule

    Owner: Planner / scheduler. Shows activities done versus total (WBS summary rows excluded), SPI at the data date (green at 0.95 or above, red below 0.85), the number of critical activities, activities behind plan, and open milestones. SPI and progress use calendar-day schedule math weighted by activity budget or duration. Open module: Enterprise Scheduler.

  5. 5

    Card 3 · Cost & Finance

    Owner: Finance manager. Shows planned budget, committed value from purchase orders, and actual cost booked against budget lines, plus open AP invoices with their outstanding total and the overdue count (red when any are overdue). Actual cost turns red when it exceeds the planned budget. Open module: ERP & Finance.

  6. 6

    Card 4 · Procurement

    Owner: Procurement lead. Shows the number of RFQs with how many are awarded, purchase orders with their combined value, and subcontracts with their combined original value. Use it to see how much of the scope is bought out. Open module: Procurement.

  7. 7

    Card 5 · Quality

    Owner: QA/QC manager. Shows open NCRs (red above three), the number of inspections, and the first-pass rate — passed items over total inspected items across all QA/QC inspections (green at 95% or above, red below 85%). Open module: Quality.

  8. 8

    Card 6 · Health & Safety

    Owner: HSE manager. Shows total incidents, OSHA-recordable incidents (red when any exist), total recorded manhours, and TRIR — recordables times 200,000 divided by manhours, the standard 200,000-hour normalization. Open module: Safety & OSHA.

  9. 9

    Card 7 · Risk

    Owner: Project director. Shows open risks, high-residual risks scoring 15 or above (red above two), and mitigations past their due date. Scores come from the risk register's residual (or inherent) rating. Open module: GRC & Risk.

  10. 10

    Card 8 · Stakeholders & Approvals

    Owner: Project director. Shows open approval workflows from the stakeholder register, overdue items where the ball is in someone's court past the due date (red when any exist), and open RFIs routed through the governance workflow. Open module: Stakeholder Register & Approvals.

  11. 11

    Card 9 · Communications

    Owner: Document controller. Shows meetings held and how many have finalized minutes. A rising count of unfinalized minutes signals meeting records are not being closed out. Open module: Meetings.

  12. 12

    Card 10 · Commercial (Client IPCs)

    Owner: Commercial manager. Shows the number of IPC claims, the total certified amount, and the total received. The received figure is badged against certified: green at 90% collection or above, red below 60%. Open module: Commercial.

  13. 13

    Card 11 · Handover & Closeout

    Owner: Project director. Shows the closeout checklist completion (done versus total, green only when complete) and open handover assets not yet handed over or accepted. Open module: Handover.

  14. 14

    Card 12 · Resources

    Owner: Project manager. Shows how many schedule activities carry a resource assignment and the total planned manhours across the schedule. Use it to confirm the schedule is resource-loaded before relying on labor histograms and leveling. Open module: Field.

  15. 15

    Not a signed baseline

    Export PMP status PDF downloads the four health measures and all twelve areas with project, data date, currency and UTC capture time. It is a status report, not a formal approved plan. Start PMP sign-off requires selecting a project-linked PMP/PEP document and creates a canonical PMP/PEP submittal draft with the twelve-area status snapshot and original document ID in immutable history. In Stakeholder Register open the draft, check content and attachment, Submit internal review, then Authorize & issue. Consultant review follows; Client Review occurs only when required in Parties & routing for PMP/PEP. Acceptance and Close record decisions, not qualified electronic signatures. Use Create revision to revise rather than overwriting prior approved content. The dashboard itself never becomes a signed baseline.

Done when

Open the dashboard for a live project: every card shows real counts, each Open module link lands on the screen that owns the data, and the four health cards match the module figures.

Important: The twelve areas are operational groupings inspired by PMBOK, not a claim that PMBOK has twelve official knowledge areas. Empty visible source sets may show zero; source request errors are displayed and prevent export/sign-off. Only records accessible to the signed-in account appear. Schedule indicators use calendar-day current-plan math, not approved-baseline EVM.

03

Start Here · Project setup

Sign in and establish access

Responsible: Administrator and project manager

  1. 1

    Sign in with your own account

    Use email sign-in or the configured Google option. Complete any email confirmation required. Do not use shared accounts for approvals or financial postings.

  2. 2

    Confirm your permissions

    Ask an administrator to verify your role in Settings & RBAC. Give planners, procurement staff, finance staff and reviewers only the permissions they need. Test access with the intended user's account.

  3. 3

    Assign each person a role from the permission matrix

    In Settings & RBAC → Employees, open an employee and choose a role. The list is grouped into Platform roles — all fifteen roles in the permission matrix, each granting the access level the matrix enforces — and Company job roles such as Project Manager or Site Engineer. The line below the list states which access level the chosen role grants, and the role editor can start a new job role from any platform role.

  4. 4

    Enable the required modules

    An administrator opens Modules & Features and activates the modules needed for this project. If a menu is missing, check both module activation and role permissions; enabling a module does not grant permission.

  5. 5

    Separate training from production

    Use demo records only for practice. Do not press Seed Demo Data in a live operational context without an agreed data-management plan. Check that financial records are visible after signing in.

Done when

Named users can access the correct modules, and an authorized finance user can read financial records.

Important: Empty financial tables can indicate missing permission or a signed-out session, not an absence of records.

04

Start Here · Project setup

Initiate and select the project

Responsible: Project sponsor and administrator

  1. 1

    Create the project

    Open Projects — Tasks & Details, expand New project below the workspace, enter a unique code, name, client, city, contract type, currency, start/finish dates and financial-year start month, then press Create project. The new project opens immediately and a ten-item closeout checklist is created automatically.

  2. 2

    Prepare the project brief

    Agree a unique project code, name, owner, location, building/floor/room structure, scope, currency, approved budget, start date and target handover date. Keep the signed brief with the project records.

  3. 3

    Choose the project in the top bar

    Choose the company project in the top dropdown. Projects immediately opens its working lifecycle with setup first. Select a stage to work on its records and tasks; expand multiple stages for comparison. The KSA lock applies only to Live Demo and explicitly opened training screens.

  4. 4

    Confirm the scope of each module

    Before entering records, inspect the project field and filters in that module. Agree who owns planning, purchasing, site delivery, finance and compliance. Do not assume every page follows the top-bar selection.

  5. 5

    Advance the lifecycle stage

    At Handover & GRC, review the closeout checklist and project lifecycle transitions: Bidding → Mobilization → Active Construction → Substantial Completion → Commercial Closeout → Archived. Stage navigation only changes the view; it does not approve or complete a stage. Completion evidence is displayed separately from task counts.

  6. 6

    Work on project tasks

    Every lifecycle stage contains its own Tasks list/board with search, status, priority, assignee and overdue filters. New task starts assigned to that stage. Edit the Lifecycle stage field to move a task between stages without copying it. Existing tasks without a stage remain visible in Unassigned project tasks. Save updates the original tasks record, and reopening a done task clears its completion date.

  7. 7

    Review all module activity

    Live records are grouped by stage and source: setup budgets/risks; design locations/drawings/submittals/transmittals; scheduling WBS/activities/milestones/calendars/baselines/delays; procurement RFQs/bids/POs/lines/subcontracts/receipts; site RFIs/daily reports/labor/equipment/meetings/actions/inspections/NCRs/punch/safety; finance changes/pay applications/invoices/payments/ledger/forecasts; FF&E items/shipments/room release; handover assets/warranties/compliance/retention. Search all records and filter by status. Open any record for all saved fields. Inline Edit saves permitted operational fields to the original source record. Approvals, signed decisions, safety calculations, room gates, payments and ledger posting remain in their secured full workflows; they are not bypassed by generic edits. Query failures appear as errors, not empty records. Each stage shows a flat table with record type, details, date, status/progress and owner/amount. Filter by record type; click a row or Details to inspect the full saved record, and use Edit for permitted changes. The four top statistics open matching source-record, completed-task, overdue-task and stage-unassigned-task lists; zero counts open an empty result rather than navigating to unrelated records.

  8. 8

    Use one working destination

    Portfolio rows and previous Project 360 or Tasks addresses open this same Projects dashboard. Work within each stage, or use its links for advanced tools and record creation. Closed projects remain read-only here. Tasks and scheduled activities are separate records; no duplicate project data is created.

  9. 9

    Upload and link real project documents

    Select the project in the top dropdown and open Projects → Documents. Choose a category (Drawings, Contracts, Submittals, Schedules, Specifications, Finance, Safety, Quality, Correspondence, Handover or Other) and optional details before uploading one or more non-empty files up to 25 MB each. Add link saves a name, secure HTTPS URL, category and optional description. Files & links is a table showing document type/category, file format (PDF, XLSX, image or link), details, size and added date. Search by name, description or category and filter by category or file format. Click a name, row or Details icon for saved metadata; use Open or Download for file access through short-lived private signed links. Administrators and project directors can add documents to open projects; closed projects are read-only. The document registers below use a single typed table for drawings, submittals, transmittals and handover records, with search, type filtering, details and permitted editing. These are the existing operational records, not duplicate uploaded documents. External links retain the provider’s own access requirements. Document format is shown separately from document type in file listings and registers. Choose View content to read PDF pages, Word .docx documents, images, text/CSV files, audio or video inside the app. PDF previews include previous/next page controls. The same secure viewer is available from CDE Files & links, attached drawing originals, document registers and message attachments. Word formatting is converted for reading, not exact print reproduction. Legacy .doc, spreadsheets and other unsupported formats use Download or Open original. External providers may block inline access or require sign-in; use Open original in that case. Register entries without an attached original are labeled No original attached and have no content-view action.

  10. 10

    Choose and maintain the project base currency

    In New project or Project setup → Project details, choose Base Currency. New projects default to SAR; existing projects retain their previous currency. Save project details to refresh the shared project settings. New estimates, requests, orders, budgets, subcontracts and financial records use the project currency where no transaction currency is specified. Existing estimates and transactions retain their saved currency: changing the project currency does not convert or reprice history. Review existing budgets and estimates separately before further posting.

Done when

An approved project brief exists and the correct project record is selected and checked in each working module.

Important: Aurora Medical Tower remains a demonstration project until real drawings, schedules, budgets and a model are supplied and validated.

05

Start Here · Project setup

Set budgets, reporting and approvals

Responsible: Project manager and finance controller

  1. 1

    Agree the original budget

    Break the approved budget into project and cost categories. In ERP, compare the displayed budget, committed purchase orders and actual costs with the signed baseline. Have an authorized administrator load missing opening records through the approved data process.

  2. 2

    Set the reporting year

    In Financial Statements, choose Financial year and Year starts. Confirm the resulting date range matches your organization's financial year before reviewing or exporting statements.

  3. 3

    Define decision authority

    Agree who may request, review, award, approve invoices and record payment. Inspect Approvals for pending decisions. Use your organization's approval limits; do not assume every business limit is automatically enforced.

  4. 4

    Record the baseline evidence

    Keep the authorized budget and starting balances with dated exports. Check that all records use the intended project and currency. Agree a weekly progress review and monthly finance review.

  5. 5

    Review project and company financial statements

    In Financial Statements select Reporting scope: a project automatically selects its base currency, while Company overall includes authorized posted entries across projects and unallocated entries. Statement currency translates amounts using dated, reference-backed transaction FX snapshots first, then historical booking rates via SAR. Future rates and current revaluation rates are not substituted. Missing historical rates suppress statement totals and list the missing conversion/date evidence; finance must supply approved historical evidence rather than assume a rate. Click Revenue, Expenses or Net profit for Profit & Loss, Total assets for Balance Sheet, and Cash at year end for Cash Flow; the corresponding total is highlighted. Aging uses the same historical conversion rules. Native journals are unchanged. This is management reporting, not statutory consolidation: closing-rate adjustments, intercompany eliminations and automated WIP/COGS relief are not added. ERP Ledger currency and cash-flow Forecast currency remain native-currency filters.

Done when

The baseline, reporting dates and approval responsibilities are agreed and documented.

Important: The year-start selection is a reporting preference stored in this browser; it does not create a legally controlled accounting year or lock postings.

06

1 · Design & Documents

Build the location hierarchy

Responsible: Project manager and BIM coordinator

  1. 1

    Create the site and buildings

    Open Location Hierarchy and add the top-level Site, then each Building beneath it.

  2. 2

    Add levels, zones and rooms

    Choose a parent and add the next level down. The page names the kind automatically: Building → Level → Zone → Room.

  3. 3

    Reorder or move sections

    Drag a location row onto another row to place it before that row under the same parent. Drop onto Move into to make it a child, or onto Top level to move it to the root. The parent selector and up/down arrows provide alternatives. Moves save immediately; reload to verify the order. The system rejects moves into the same location, its descendants or a different project. Location kinds remain unchanged when moved.

  4. 4

    Use the same names everywhere

    Use these exact location names on RFIs, punch items, NCRs, FF&E rooms and handover assets so reports line up.

Done when

Every room on the drawings exists in the hierarchy under the correct level and zone.

Important: Removing a location also removes everything beneath it.

07

1 · Design & Documents

Blueprints, documents and approval stamps

Responsible: Document controller

  1. 1

    Use one hub

    Drawing register, spec book, approval stamps, transmittals/as-builts and document AI are tabs on one page.

  2. 2

    Sign stamps in order

    Subcontractor, then GC, then Architect/Engineer, then Owner. Each signature locks to the one before.

  3. 3

    Send documents for external client review

    In CDE → Client reviews, create a review link: give it a title, the reviewer's name and validity in days, and tick the project documents to include. Copy the secure link and send it to the consultant or client. They open it without signing in, view each file, leave comments per document or overall, and submit a formal decision — Approved, Approved as noted, Revise and resubmit, or Rejected. The decision and every comment are stored against the project and shown on the link card. Links expire automatically and can be disabled at any time.

  4. 4

    Project records and removal

    CDE shows only the selected project. Client reviews are handled through Stakeholder Register; Transmittals is now in Handover. Admin, Project Director and Document Controller can remove any drawing from the register (whatever its status), with confirmation and an atomic audit snapshot; the original file stays in Files & links. Removal preserves the original in Files & links.

Done when

Important:

08

1 · Design & Documents

Upload and publish drawing sets

Responsible: Document controller and design coordinator

  1. 1

    Prepare the approved PDF set

    Obtain the actual drawing issue with its revision, date and discipline. Use a readable PDF and retain the original file. A scanned page may not provide extractable sheet identifiers.

  2. 2

    Upload and review every sheet

    Choose Upload drawing set (PDF). Review the split pages and extracted sheet number/title. Correct or resolve ambiguous identifiers before relying on the drawing index.

  3. 3

    Publish the reviewed issue

    Use Publish latest to drawing log. Reopen the published entries and verify sheet identifiers and revisions. Keep the original set available through your approved document-storage process.

  4. 4

    Review changes and questions

    Upload the next revision and use Compare to inspect differences. Check detected callout links manually. Use Pin RFI on a sheet to identify a question, then verify the resulting RFI in Construction (PMIS).

  5. 5

    Measure the selected sheet

    Open a PDF drawing set or Load sample drawing set, select a sheet, then choose Measure this sheet. Takeoff opens the same original and page without re-uploading. Uploaded originals are saved in private project storage and appear in Projects → Documents. Save sheet details stores title edits; Save drawing notes stores sheet-specific notes. Reopen the project to verify the saved drawing, notes and revisions.

Done when

The current drawing issue is checked, published and traceable to its original PDF and any related RFIs.

Important: Sheet extraction and callout detection require human review. Verify original-file retention separately; publishing a drawing-log entry alone does not prove the original PDF is durably stored.

09

1 · Design & Documents

Measure quantities and review the model

Responsible: Quantity surveyor and BIM coordinator

  1. 1

    Select the correct revision

    From Drawing Management, select a sheet and choose Measure this sheet. Alternatively, choose a private saved original using Choose from Drawing Sets in Takeoff, open your PDF directly, or use Load sample PDF / Sample Rev B for testing. JPG and PNG are separate optional uploads. Confirm the source revision, sheet and units, then calibrate before measuring. Drawing Management uploads are stored privately for the selected project; older browser-cached originals remain available locally.

  2. 2

    Calibrate against a known dimension

    Select Calibrate, click the two ends of a known dimension on the current page, enter its actual length and unit, and Apply scale. Each page has its own saved scale; an uncalibrated page remains explicitly warned. Measure a second independent dimension and a known rectangular area before relying on quantities. Zoom does not change values or move saved geometry away from the drawing. Recalibrating a page recalculates its existing length/area measurements; saved BOQ snapshots do not silently change and must be reviewed separately.

  3. 3

    Record and check quantities

    Measure by package or room, give each result an identifiable description, and review quantities with a second person. Press Save measurements to store measurement geometry, labels, calibration and zoom against this project and drawing. Reopen the same saved original or sample to restore the canvas. Use an available export or your approved quantity register for the handoff to FF&E and procurement.

  4. 4

    Price and save the Bill of Quantities

    Below the Takeoff canvas, use Priced Bill of Quantities. Add current measurements to retain drawing, page, measurement ID and measured quantity, or add manual items. Edit descriptions, cost codes, quantities, individual unit rates and waste percentages. Create reusable project rates in Unit rates; only matching units and currencies are offered. The estimate starts in the project currency; choose another currency before adding lines. No currency conversion occurs. Save estimate stores the BOQ in the database; choose it from Saved estimates after returning or reloading. Loading another drawing does not delete saved BOQs. Save measurements separately stores the canvas geometry and calibration; saved BOQs remain the priced quantity register.

  5. 5

    Review allowances and hand off to procurement

    Each line amount is quantity times (1 + waste percent / 100) times unit rate, rounded to two decimals. Direct cost sums those amounts. Overhead/profit and contingency are each calculated independently on direct cost, rounded to two decimals, and added to the total; tax is excluded. Export priced CSV includes cost codes, quantities, rates, drawing/page references and allowances. Create RFQ from BOQ first saves the estimate and creates a real project-linked draft RFQ with its currency, full priced scope and estimate reference. Every RFQ line must have a positive quantity and rate; no comparison bids are fabricated. Open RFQ workflow and select the created request. Database permissions and closed-project checks govern edits and handoff.

  6. 6

    Inspect model-to-scope references

    Export IFC from Revit, Tekla or ArchiCAD in agreed units and shared coordinates. BIM → Model Library & BOQ stores the original privately per selected project and measures geometry automatically on upload. Reopen saved models in the 3D Viewer after reload; direct viewer-only IFC/GLB/GLTF imports remain session-only. Live Autodesk access, native RVT reading and background synchronization are not connected.

  7. 7

    Manual PDF ratio and automatic calibration saving

    For a PDF printed at a verified sheet scale, choose Manual scale 1:n and enter the denominator (100 for 1:100). Base coordinates use physical PDF points independent of zoom. Applying manual or two-point calibration recalculates current-page measurements and saves that page scale immediately to the project drawing workspace. Images still require two-point calibration because image resolution does not establish a physical print scale. Save measurements after further geometry/label edits. Verify a second dimension and area; no real BOQ validation is claimed.

  8. 8

    Load the IFC coordination sample

    BIM → 3D Viewer → Load sample IFC model (or Download sample IFC) loads three training elements. Run Clash Detection yields one intentional beam–duct collision with within-model checks enabled. Inspect both source IDs in Clash Matrix and focus the pair. This fixture is not a real building or the selected project design; do not create operational RFIs from training evidence.

  9. 9

    Structural sample and automatic unpriced BOQ

    BIM → Model Library & BOQ → Load structural sample & extract BOQ stores a clearly labelled synthetic IFC structural frame and automatically measures 12 elements: four footings (8 m³), four columns (1.92 m³), two beams (1.44 m³), one slab (4.8 m³) and one floor covering (24 m² projected face). Concrete total is 16.16 m³. Structural types include separate gross surface and count rows; these are not net finish/formwork entitlements. Open in 3D, review quantities, download CSV, then Create draft estimate. All lines remain unpriced; pricing/approval stay in Estimating. This is a Revit-compatible IFC training fixture, not a native .rvt or provenance-verified Revit export. Qto values, material-aware concrete classification, robust open-shell validity, slope corrections and full revision delta remain limitations.

Done when

Reviewed quantities identify their drawing revision, units, room/package and reviewer.

Important: Save measurements persists geometry and page-specific calibration to private project drawing workspaces. Save estimate separately persists priced BOQ quantities. No user-supplied real BOQ and dimensioned drawing were available for Phase 6 verification; the dimensioned reference test is synthetic, not actual project evidence.

10

1 · Design & Documents

Estimating — Rates, Crews, Quotes & Budget Baselines

Responsible: Estimator and quantity surveyor

  1. 1

    Build the full estimate in Estimating

    Open Estimating from 1 · Design & Documents (or the Estimates & versions record in Projects → Design stage). Choose a saved Takeoff BOQ or start a new estimate. Assign each line a CSI section and cost code, then open Build-up to enter material per unit, labour hours per unit and labour rate, plant hours per unit and plant rate, and subcontract per unit; the unit rate is calculated automatically. Add preliminaries and indirect costs (site establishment, cranes, supervision, insurance, bonds). Overhead/profit and contingency apply to direct cost only; tender total = direct + indirects + overhead/profit + contingency, tax excluded. Review cost by type (material, labour, plant, subcontract), labour hours and cost by section.

  2. 2

    Reuse shared crews and productivity

    Open Crew & escalation library in Estimating. Save a named crew with its output unit, output per crew hour, member counts and hourly rates, and plant cost per crew hour. Templates are private to the selected project and reusable across its estimates; only matching currency/unit templates are offered. Under a line’s Build-up & quotes choose the crew: man-hours per unit = total crew members / hourly output; labour hourly rate is the member-weighted average; plant hours per unit = 1 / hourly output. The derived build-up is a snapshot, not a live link: later template changes do not reprice saved estimates. m3 (cubic metres) and ft3 are available for manually entered volume quantities and library rates. The 2D drawing canvas still measures length, area and count; volume quantities must be entered or calculated separately.

  3. 3

    Apply planned escalation

    Save reusable annual escalation profiles or enter an annual percentage and months from base pricing on each line. Escalated unit rate = base rate × (1 + annual percent / 100)^(months / 12), rounded to two decimals. The original base rate is retained, so changing the horizon does not compound escalation twice. Escalation applies proportionally to cost components, not to labour hours. The controls accept 0–100% annual growth and 0–120 months. These are planning assumptions, not live market indices; preliminaries remain separately entered amounts.

  4. 4

    Compare supplier quotations

    Under Build-up & quotes enter supplier name, quote reference, received date, unit rate and exclusions for each offer. Quote currency and unit match the line. Compare the rate and variance against the current estimate rate; Use rate adopts that offer as a flat full-line rate, clears its old crew/build-up/escalation, and retains the selected quote and competing quotations as evidence. It is not a subcontract-component-only replacement. Save the estimate to retain quotations. This is manual per-line quote comparison, not an automated provider feed, quote-document parser or formal vendor award; use procurement RFQ and Bid Leveling for invitations and awards.

  5. 5

    Review, approve and baseline the budget

    Submit for review, then an authorized administrator or project director approves. Approved estimates are locked. Push to project budget opens a reconciliation preview: previous/new planned amounts, commitments and actuals. Confirm replacement baseline updates only this linked estimate family’s source-tagged budget lines, preserves actual/committed values and manual budgets, and records an immutable baseline snapshot. Removed categories retain financial balances with zero planned cost. Estimate currency must match project currency. New version creates a linked draft; save and approve it before replacement. Unrelated estimate families add separate scope and must not overlap. Legacy baseline rows are tagged only where title/project matching is unambiguous; ambiguous historical rows require review.

  6. 6

    Control access and inspect revisions

    Project access lets administrators, or an existing edit-authorized project director, grant read/edit access to registered users. Membership does not grant global author/approval roles. Administrators retain access. Existing estimate creators were granted edit membership; other collaborators must be explicitly granted. Source estimates, project rates and templates are protected; deliberately published RFQ/budget values continue using their operational permissions. Revision history shows actor, time, action and immutable read-only snapshots. New version links to its parent. Both Takeoff and Estimating reject stale saves; unsaved edits remain available, and Reload latest explicitly discards them after confirmation.

  7. 7

    Run the sample revision exercise

    In Live Demo, open the existing Estimating step and choose Sample · Revision and reconciliation exercise · v2. Review Revision history and the budget preview; it is approved but has not been pushed into the KSA budget. A separate Sample · Estimating reconciliation lab project shows two baselined linked estimates: planned concrete changes from SAR 1,000 to 1,200, retaining SAR 800 committed and SAR 600 actual, plus a separate SAR 99 manual plan. These are fictional training records, not company financial results.

  8. 8

    Reuse past rates from the Historical Rate Library

    Open Build-up & quotes on an estimate line and choose Historical rates. The library lists rates with the same unit and currency from approved or baselined estimates (excluding the one you are editing), the supplier quotes recorded on them, and issued purchase orders you are allowed to see. Search by description or cost code; lowest, average and latest rates are shown with project, supplier, reference and date. Enter an annual inflation index to escalate each rate from its date to today (rate × (1 + % / 100)^years). Use rate sets the line's flat unit rate, removes any build-up, and saves the source as rate evidence on the line. Typing a rate manually clears that evidence. No currency conversion or external cost database is used.

Done when

The estimate shows composite rate build-ups per line, section totals, preliminaries, overhead/profit and contingency, and an approved version can be pushed to the project budget with a replacement preview.

Important: Functional estimating with project access, immutable revision snapshots, stale-save protection and linked-family baseline reconciliation is available, but this is not enterprise-scale certification. Saves at very large line counts (50,000+) can exceed database time limits; split very large tenders into package estimates.

11

2 · Scheduling

Establish and review the delivery schedule

Responsible: Planner and project manager

  1. 1

    Open or create the project in Projects

    Enterprise Scheduler → Projects shows the EPS tree and every project with start date, status, last imported and last exported. Add project needs a unique Project ID, name (also the schedule name), start date and EPS. Import accepts XER, Primavera XML or Excel; a summary lists activities, WBS, relationships, warnings and errors, and the file is staged until you assign it under Files & history. Export writes XER, XML or Excel. Open makes the project active in every scheduler tab.

  2. 2

    Work in Activities & Gantt and Schedule Analysis & Controls

    Click an activity to populate the docked bottom details pane (no Details column). Drag the table/Gantt divider and bottom-pane divider to resize; vertical row scrolling stays synchronized. Schedule recalculates CPM (F9), Baselines opens the existing baseline controls, and Critical only filters the display without changing the schedule. Columns opens a categorised chooser; drag header edges to resize. Remaining duration and forecast finish are calculated. Schedule Overview holds the summary indicators. Schedule Analysis & Controls holds Multi-Calendar & Baselines, Look Ahead, Resource Management & Leveling, What-If Scenarios and Delay Analysis & TIA. Earned Value & Risk is in Scheduling Pro.

  3. 3

    Validate activities and WBS

    Open Enterprise Scheduler or Schedule Control and choose Add activity manually. Enter a unique activity ID, name, WBS code, duration, activity type, optional predecessor and calendar, then Save activity. Add WBS section creates a named work-package section. Manual and imported activities share the same project schedule records. Reopen the form and confirm the saved activity appears as an available predecessor, or review it in the Enterprise Scheduler activity table. Confirm durations, predecessor relationships and calendars against the approved schedule.

  4. 4

    Choose activity types deliberately

    Use the activity-type selector for Task Dependent, Resource Dependent, Start Milestone, Finish Milestone, Level of Effort or WBS Summary as appropriate. Check how the change affects calculated dates and float.

  5. 5

    Check resource pressure

    Open Resources & leveling. Review demand against limits, then choose Level resources (within float) if approved. Compare the revised dates and unresolved overloads; use Clear leveling if the result is unsuitable.

  6. 6

    Test a change before committing

    In What-if, enter proposed delays, inspect finish impact and Save scenario. Load a saved scenario to review it. Use Merge into live schedule only after authorization, then reopen to verify the saved result.

  7. 7

    Organize the enterprise structure (EPS)

    Open Enterprise Scheduler → EPS. Administrators and project directors choose Add EPS to create enterprise nodes, +EPS or +Program on a node to nest levels, Rename or Delete to maintain them, and drag a node onto another (or the root drop zone) to reorganize — the database prevents circular moves. Assign each project to a node using the selector on its row; unassigned projects are listed at the bottom. Every node rolls up its whole subtree: project count, total capex and average progress.

  8. 8

    Build the WBS and add activities under it

    Open Enterprise Scheduler → WBS tree. Choose Apply standard construction WBS to add the industry phases (Preconstruction, Design, Procurement, Substructure, Superstructure, Envelope, MEP, Fit-out, FF&E, Commissioning, Handover) — existing sections are kept and unnamed imported codes receive names. Add your own sections with Parent + New WBS name, or + Child on a row; Rename or Delete as needed (a section with child sections or activities cannot be deleted). Choose + Activity on a WBS row to open Add activity manually with that WBS selected. In Activities, filter by WBS to see only that section.

  9. 9

    Review all enterprise activities

    Open Enterprise Scheduler → Enterprise activities to list scheduled activities across every project. Filter by EPS or program (includes nested nodes), project, activity type, status, critical only, or search by ID, name, WBS or resource. Dates and float are calculated per project.

  10. 10

    Exchange schedules with Primavera

    In Schedule Control, export the schedule to an .xer file or import one; activities, WBS, types and logic (FS/SS/FF/SF + lag) are saved.

  11. 11

    Status with a data date

    Set the data date and save. Incomplete work is pushed forward and the forecast finish and variance are shown.

  12. 12

    Analyze delays

    Record a delay fragnet after an activity with its cause and duration. The completion impact is calculated; contractor-caused delays are marked Not Entitled for extension of time.

  13. 13

    Simulate active risks before recording a formal delay

    Enterprise Scheduler → Schedule Analysis & Controls → Delay Analysis & TIA opens the Risk-to-fragnet delay simulator above the formal delay register. Select active risks with schedule impact days, or use Simulate all active linked risks. The tool inserts temporary delay fragnets and runs current and impacted calendar-aware CPM with the same leveling shifts. Risks on one activity accumulate sequentially in risk-ID order. FS/FF successors follow the fragnet; SS/SF successors keep their original start anchor and lag. Review current/simulated finish, elapsed and working-day delay, approved-baseline variance, one traced critical route and changed activities. Working-day delay uses the simulated finishing activity's named calendar; float can absorb risk days. Unlinked, inactive, invalid and non-driving-anchor risks are excluded with reasons. This combined deterministic scenario is not Monte Carlo analysis, an extension-of-time decision or a saved TIA. Nothing is written to activities, risks, baselines or delay events; use the formal delay register below only after review and authorization.

  14. 14

    Work in the unified WBS/activity workspace

    Enterprise Scheduler → Activities combines collapsible WBS sections and their activities. Create activities from the selected WBS row. Select an activity row, Details or its Gantt bar to open an immediate on-screen six-tab inspector. Save actual dates, remaining duration, forecast finish and Physical, Duration or Quantity progress; saves use conflict checks and record audit history. Calendar IDs and names resolve to working days and holidays for all four relationship types including lead/lag. PV/EV/SPI use current scheduled budget and progress; AC comes from project budget actuals, not invented activity actual costs. These values are not a certified earned-value baseline report.

  15. 15

    Save, approve and compare the project baseline

    On Schedule — WBS & Activities, open Activities & Gantt. Set the Data Date, then choose Save current schedule as baseline. Each baseline is a frozen copy of dates, durations and budgets and is sent to My Approvals; only a project director or administrator can approve it. The most recent approved baseline becomes Active. Use Baseline vs current to see start/finish variances per activity and the project finish slip. Routine progress updates never change a saved baseline; to revise it, save a new baseline and approve it.

  16. 16

    Activities table, columns and Gantt chart

    The table shows Activity ID, Activity Name, Original Duration, Planned Start/Finish (from the active baseline), Actual Start/Finish, Scheduled % at the data date, Performance % and Cost (budget / earned). Use Columns to show, hide or reorder these and the optional Remaining Duration, Total Float, Activity Status and Finish Variance columns; your choice is remembered on this browser. The Gantt chart on the right shows baseline (gold), current (teal; red when critical) and actual progress bars, relationship arrows and the data date line, with Daily, Weekly and Monthly views. WBS rows use distinct hierarchy color bands and collapse or expand the table and the Gantt together. The bottom activity inspector remains docked; its close button hides it, and Activity details reopens it.

  17. 17

    Activity details panel

    Click an activity row, Details, a matching record in a statistic drill-down, or its Gantt bar to open an immediate on-screen inspector with six tabs: General (name, duration, WBS, type, calendar), Status (actual start/finish, forecast finish, % complete, remaining duration, early/late dates and float), Relationships (predecessors and successors with FS/SS/FF/SF and lag), Resources, Costs (baseline and current budget, earned value, remaining and variance) and Activity Codes. Saving recalculates the schedule immediately.

  18. 18

    Earned Value & Risk

    The Earned Value & Risk tab calculates PV against the approved baseline at the data date, EV from physical % complete × activity budget, and AC from recorded expenditures on the project budget. It shows SV, CV, SPI and CPI, an S-curve of planned, earned and actual cost, and risk flags for negative float, critical delays, finish slips against baseline and activities 20% or more behind plan.

  19. 19

    Look-ahead risk warnings

    Enterprise Scheduler → Look-ahead lists open activities in a 2, 3, 4 or 6-week window from the data date and now shows Risk warnings. A warning appears when a risk in Risk & Compliance is Open, Accepted or Transferred, has schedule impact days above zero and is linked to an activity inside the window. 'Exceeds float' means the impact is larger than the activity's total float or the activity is critical; 'Within float' means spare time should absorb it. Mitigated and Closed risks do not warn. Risks with schedule impact but no linked activity are listed as project-level warnings. Link a risk by editing it in Risk & Compliance and choosing Schedule activity at risk and Schedule impact (days). The CSV export includes the warnings. Warnings do not change dates; use delay events/TIA to model a delay formally.

  20. 20

    Inspect statistics and interact with the Gantt

    Activities, Project finish, Critical and Leveling shifts open paginated lists of exactly matching schedule records. Select any listed activity for its six-tab inspector. CPM calc shows the real calculation status and permits recalculation; no fabricated timing is shown. Hover or keyboard-focus a Gantt bar for dates, working duration, total/free float, progress, baseline finish variance and assigned resource. Selecting a critical activity highlights its connected critical dependency chain; Clear critical trace removes the highlight. Click or keyboard-activate a dependency arrow to open the successor Relationships tab and use the existing link editor. Drag the right finish handle of an unstarted Task Dependent bar (or use arrow keys on the handle) to preview a new duration. Working days and holidays are counted using that activity calendar. Apply duration uses the existing project-scoped conflict-checked save and refreshes CPM, while Discard resize writes nothing. Started/completed activities, milestones and derived-duration types are inspect-only on the chart. This is duration resizing, not free date movement or drag-to-create links; baseline snapshots and other module workflows are unchanged.

  21. 21

    Calendar & Baseline workspace

    Activities & Gantt retains the Data Date control. Create, compare and approve baselines in Calendar & Baseline. Import baseline from XER creates a pending baseline snapshot without replacing live activities. Project-director approval makes it available for comparison. Scheduling Pro reads the same live activities, approved baseline, project budgets and currency.

Done when

The reviewed schedule has an agreed finish date, critical path, resource assumptions and authorized change history.

Important: The scheduler uses the selected project. Verify imported calendars, calculations and XER files against the approved schedule; this is not a certified replacement for every native Primavera feature.

12

2 · Scheduling

Calendars, baselines and delay analysis

Responsible: Planner

  1. 1

    Assign calendars

    Give each activity its own work calendar (6-day, 24-hour, Ramadan hours or standard). Add custom calendars and holidays.

  2. 2

    Calculate and baseline

    Run the schedule, then save a baseline (B1, B2) before changes.

  3. 3

    Run delay analysis

    Insert each delay event one at a time; results split into owner, neutral and contractor days. Delays on non-critical work correctly show 0 days.

  4. 4

    Auto-level resources with a preview

    In Enterprise Scheduler → Resources & leveling, set each resource's daily limit (or create the dictionary from activities at peak demand). Click Auto-level resources (preview): the engine computes a leveled schedule that delays activities only within their total float and lists exactly which activities would move, from which start date to which, and by how many days. Apply leveling writes the shifts to the schedule; Discard keeps the current plan. Clear leveling removes all shifts in one click.

  5. 5

    Reverse level to a deadline

    In Enterprise Scheduler → Resources & leveling, click Reverse level to deadline (preview) when the finish date must not move. Critical work stays on its dates; every other resource-loaded activity is placed as late as its float allows and then pulled earlier, latest first, until its resource fits the daily limit. The preview lists each activity that moves (negative days = starts earlier, positive = later within float), confirms the finish held, and names any resource that still cannot fit without extending the finish — add capacity or accept a later finish with forward leveling. Apply writes the result; Discard keeps the current plan.

  6. 6

    Stage, assign and unassign XER schedules

    Open Schedule Control → Project XER file library; select multiple XER files. Upload archives the source without changing live records. Assign publishes activities, WBS, calendars, resources and assignments atomically into an empty workspace. Existing schedule records are protected. Unassign clears only an unchanged, unprogressed staged schedule without operational links; edited, progressed or BOQ/quantity-linked schedules cannot be cleared. Original files remain archived. Export uses the selected project, retained extra data and currency. Review imported calendar work weeks/holidays before using the schedule.

Done when

Important:

13

3 · Procurement

Qualify vendors and check third-party risk

Responsible: Procurement lead and compliance reviewer

  1. 1

    Procurement register (live project records)

    Procurement shows only the project picked in the top selector, read directly from the database: RFQs with invited vendors and bids, purchase orders with lines, delivery destination, goods receipts and AP invoices, shipments, and the vendors used on the project. Summary cards (open RFQs, awarded value, value in flight, open purchase orders) are calculated from those records in the project currency. New RFQ and Import create Draft RFQs on the project; inviting vendors, recording bids, award, PO issue, shipment booking, receipt and settlement continue in the RFQ workflow so commitments and ledger postings happen once. Only Draft RFQs without invited vendors can be deleted. Admins, project directors and procurement leads can advance a shipment Booked → In Transit → At Customs → Delivered; delivery does not replace a goods receipt. The earlier sample-data procurement screen, its fixed savings figure and AI recommendation were removed.

  2. 2

    Create and maintain the shared vendor master

    Administrators and procurement leads choose New vendor or Edit vendor in Vendor Profiles. Save contact details, categories, tax reference, payment terms, currency, status and credit limit. Requisitions, purchase orders and invoices use this same vendor record. Only Approved vendors can receive a purchase order from a material requisition. Vendor accounts remain isolated from internal project requests and other vendors' purchasing.

  3. 3

    Check the vendor's identity

    Open Vendor Profiles and review contacts, country, payment terms, credit limits and performance history. Verify the actual supplier and bank details independently before payment.

  4. 4

    Review risk and insurance

    In GRC Audit, inspect Third-Party Risk (TPRM). In Commercial Controls, check certificates of insurance and relevant expiry dates. Keep verified supporting evidence, not just a status label.

  5. 5

    Agree the bidding shortlist

    Select suppliers able to meet specification, lead time, quality and compliance requirements. Resolve any holds or missing evidence before awarding work.

  6. 6

    Confirm vendor-facing access

    Use Vendor Portal only with the intended vendor account and verify the RFQs and records visible to that account. Check that a vendor cannot view unrelated suppliers' records.

Done when

The bidder shortlist and supplier evidence are approved before an award is made.

Important: Policy/TPRM screens include demonstration interactions; a reminder, override or email toast is not proof that an assessment or message was saved or delivered.

14

3 · Procurement

Request materials and link purchasing to the budget

Responsible: Requesting staff, procurement lead and financial approver

  1. 1

    Prepare a multi-item request

    Select an open project, choose New requisition and enter the title, required date, optional vendor and optional project budget. Add each material with its specification, unit, quantity, unit price and cost code. Save draft and reopen its reference to verify all items and the total excluding tax. Currency follows the project; rates must already be expressed in that currency. Quotes are optional supporting evidence, not a required budget baseline.

  2. 2

    Submit, approve or return

    Save changes before Submit. Administrators, project directors and finance approve submitted requests or reject with a decision note. Requests of 50,000 or more require a project director or administrator; 250,000 or more require an administrator, matching existing purchasing thresholds. Drafts and rejected requests remain editable by their creator or procurement managers. Submitted and approved items cannot be silently repriced; concurrent saves are rejected.

  3. 3

    Issue once and verify finance

    After approval, an administrator or procurement lead chooses Issue purchase order. The vendor must be Approved and items priced. The purchase order and all quantities, units, rates and cost codes are created together. The issued total becomes a commitment on the chosen project budget, or the Procurement budget if no budget was selected. Requests themselves do not create financial commitments. Qualifying approved/paid AP invoices linked to that PO update actual cost on the same budget through existing finance postings. Receipt, stock, invoice matching and payment continue in SCM and ERP; no receipts or payments are fabricated. Open Projects → Procurement to inspect the requisition and its canonical PO lines.

  4. 4

    Specify the receiving destination

    Select Receiving warehouse, a Project delivery location from that project’s hierarchy, and/or a Delivery address / manual override. Save these with the material request; the approved request copies them to its issued purchase order. A location from another project is rejected. Once an order is issued its destination cannot be edited; resolve changes through the agreed purchasing process.

Done when

Important: Plan less commitments is informational, not a hard spending limit. This is a single-vendor requisition with multiple items; formal competitive bidding remains in RFQ Workflow. It does not perform currency conversion or external ERP synchronization.

15

3 · Procurement

Run an RFQ and award a purchase order

Responsible: Procurement lead and award approver

  1. 1

    Define the request

    Open RFQ Workflow (End to End). Create or select the request for the intended project; review item scope, quantities, specifications, delivery requirements and bid due date.

  2. 2

    Invite bidders and capture actual responses

    Progress through invitation and bid stages. Record actual vendor quotes and their inclusions, exclusions, currency, freight, tax and delivery dates. Verify invitation delivery separately if no live messaging connection is configured.

  3. 3

    Level and score the bids

    Open Bid Leveling and confirm the selected project. Choose its RFQ package; canonical rfq_bidders quotations and recorded vendor ratings are loaded, not sample offers. Compare price, RFQ currency, lead days and notes/exclusions. Change price, lead, recorded reliability and ESG weights for advisory evaluation; a missing weighted criterion prevents ranking rather than inventing a score. ISO 9001 is not an ESG score. Choose AI Award Analysis & Rationale to rank up to 20 complete canonical offers with those same displayed weights and currency. The authenticated server rereads the project RFQ and offers; it does not trust a browser-supplied recommendation. Review ranked offers, exclusions and recorded risk basis. The AI is instructed to cite only supplied evidence; if narrative generation fails, the window explicitly labels the result Deterministic fallback and shows the safe error instead of presenting it as AI. Refresh bids reads current records; this is not a streaming carrier or vendor feed. Download PDF/CSV comparison if needed, then Review / award in workflow opens the same RFQ for the authorized human decision. AI analysis never changes award status. Confirm equivalent tax, freight and scope before award.

  4. 4

    Authorize the award and check the PO

    An authorized user awards the selected bid. Reopen the resulting PO and verify vendor, project, lines, total and delivery terms. Check any generated shipment reference before proceeding to logistics.

Done when

A reviewed bid comparison, authorized award and traceable PO exist for the agreed scope.

Important: The quick RFQ → PO Wizard includes generated comparison bids. Use actual submitted quotes for a real award; do not mistake demo prices for offers.

16

3 · Procurement

Buy out trades with master subcontracts

Responsible: Commercial manager

  1. 1

    Register each subcontract

    Add title, trade, CSI MasterFormat code, vendor, contract value and retention percentage.

  2. 2

    Update cost monthly

    Use Update cost to enter billed to date and forecast to complete. The page shows committed, estimate at completion, variance and retention held.

  3. 3

    Release retention

    Request a partial or final release. Approval is blocked until punch is cleared; final release also needs the unconditional final lien waiver. Paying the release reduces retention held.

Done when

Every trade has a subcontract, and negative variances have a recovery plan.

Important: The database blocks retention approval without punch clearance — this is intentional.

17

4 · Construction Site

Manage site work, RFIs and submittals

Responsible: Site manager and design coordinator

  1. 1

    Record daily site progress

    Open Daily Progress · Labor & Equipment → Daily Progress & Quantities for the selected project. Configure an activity quantity basis from a saved same-project BOQ line, or enter a manual planned quantity, unit and rate. Select an existing schedule activity; Add schedule activity opens the existing scheduler for new activities. New DPR records multiple activity quantities, date, crew count, hours, weather, narrative, delays and evidence references. Save DPR draft, reopen it and review planned, previous, period, cumulative, remaining and percentage values. Approve quantities locks the report and updates the same activity percentage used by the schedule and Command Center. Drafts do not affect progress; approved cumulative quantities cannot exceed the plan. Multiple quantity bases on one activity are combined as the equal-weight mean of individual completion ratios, not a sum of incompatible units. Field timecards/equipment also follow the selected project. Add labor rows for each trade, project subcontract (or Direct workforce), zone and Day/Night/Split shift. Enter headcount and regular/overtime hours per person. Ten people at eight hours plus two overtime hours produces 100 person-hours. Manpower totals derive from the rows; headcounts represent crew-shift entries rather than unique employee identities. Rows save atomically with quantities, persist after reopening and lock on approval. These summaries are not payroll or automatic ERP cost postings; detailed timecards remain separate. New offline DPR drafts include their labor breakdown and use the same validation on sync.

  2. 2

    Resolve design questions

    Create an RFI with a clear question, drawing reference, responsible reviewer and due date. Track the response and communicate the decision to affected teams before closing the RFI.

  3. 3

    Track submittals and defects

    Maintain the submittal log and confirm approvals before installation. Use punch items to record defects, assign owners and verify remedial work. Review overdue items in Construction Pro.

  4. 4

    Record meeting decisions

    Select the project in the top bar, then open Meetings & Minutes. Next meeting creates a draft and carries open actions from the selected previous meeting without changing its finalized record. Edit title, date, attendees, location, minutes, agenda, decisions and actions with owners/deadlines. Save draft before Submit for review. Administrators and project directors Finalize minutes or Return to draft. Final minutes and items are locked; Create revision opens a new editable draft and retains the prior finalized snapshot in Finalized revision history. Stale saves are rejected. Meeting edits and review need a connection; old queued meeting-item writes cannot bypass these locks.

  5. 5

    Capture site photos from a phone

    Field Labor & Equipment is mobile-first: timecard and equipment forms stack full-width on a phone. The Site photos tab opens the device camera (or photo picker) and saves each photo straight into the project's private Documents under category Other as a Field photo, where the whole team can preview it. Photos need a connection; timecards and equipment logs still save on-device while offline and sync when back online. The app can be installed on a phone home screen from the browser prompt; offline caching only activates on the published site, never in the editor preview.

Done when

Site progress, design decisions, submittal approvals and open defects are current and accountable.

Important: Offline support covers supported queued operations, not every page or action. Verify synchronization before relying on offline records in reports.

18

4 · Construction Site

Sign off inspections and hold points

Responsible: QA/QC manager and required signatories

  1. 1

    Create the appropriate inspection plan

    Open Action Plans & Hold Points and choose the relevant template, such as Pre-Pour Concrete, MEP In-Wall Rough-In or Structural Steel Torque. Confirm the project and work location.

  2. 2

    Inspect each step

    Perform the actual inspection, record results and retain supporting evidence. Do not sign a step merely because it is next in the list.

  3. 3

    Obtain required hold-point approval

    Have the designated signatory approve the hold point before downstream work proceeds. If progress is blocked, resolve the unsigned hold point rather than attempting to bypass it.

  4. 4

    Close exceptions

    Record failed checks as punch items or RFIs as appropriate. Repeat the inspection after correction and verify the final plan status and sign-offs.

  5. 5

    Issue transmittals

    Log every formal document issue in the transmittal register and mark it Acknowledged when the recipient confirms.

  6. 6

    Manage non-conformances

    Raise an NCR, then advance it: Root Cause Identified → Disposition Set (Rework, Repair, Accept As-Is or Reject) → Re-inspection → Closed.

Done when

All required inspections and hold points are signed, with unresolved defects explicitly tracked.

Important: Database hold-point enforcement does not replace a qualified inspector's professional judgment or statutory certification.

19

4 · Construction Site

Safety log and ISO witness points

Responsible: HSE manager

  1. 1

    Log incidents

    Mark recordable cases and days away/restricted; TRIR, DART and LTIR calculate from hours worked.

  2. 2

    Witness hold points

    An ISO hold point cannot be signed until the witness signs.

Done when

Important:

20

4 · Construction Site

Use Project Twin, Digital Twin and Global Map

Responsible: Project manager and asset/facilities coordinator

  1. 1

    Review the project-wide picture

    Project Twin summarizes lifecycle milestones and commercial records. Open a milestone or summary to inspect the associated FF&E, RFQs, POs and shipments. Confirm figures against source records.

  2. 2

    Inspect asset-level status

    Digital Twin shows demonstration assets, local thresholds and sample telemetry, not live BMS readings. Use Project Twin for source operational records and Handover for canonical physical assets.

  3. 3

    Set thresholds and investigate exceptions

    Sample threshold edits and Refresh sample are isolated demonstrations. Open project RFIs or Asset Register links to inspect canonical evidence; sample refresh does not write RFIs or generate a facilities export.

  4. 4

    Review geographic exposure

    Open Portfolio Map and click a project portfolio row to open that project’s working lifecycle dashboard. Map markers continue to show a geographic snapshot.

  5. 5

    Run geometric clash detection

    Import real IFC geometry in BIM Coordination → 3D Viewer. In Clash Matrix choose the overlap filter (default 10 mm), required clearance (default 50 mm) and whether to check pairs within one IFC model. Run geometric detection checks visible IFC elements only; sample and GLB geometry are excluded. Bounding boxes identify candidates, then triangle intersections with solid checks, containment parity and actual surface distance flag collisions or clearance gaps. The overlap filter is not an exact penetration-depth measurement. Open/non-manifold shells need coordinator review. Source coordinates remain unchanged by Explode; the viewer stays loaded across tabs. Select a clash to inspect both GlobalIds and open its pair in 3D. Create linked draft RFI saves model fingerprints, source identifiers, check settings and coordinates in the canonical project RFI question; or attach an existing same-project RFI and open its workflow. No RFI is submitted or approved automatically. Repeated scans retain pair links without duplication and never automatically resolve historical issues. Results are browser/project-local; original IFC files remain session-only. Scans explicitly report incomplete when reaching 5,000 results or 200,000 candidate pairs. Large federations and owner acceptance remain unverified.

Done when

Management summaries can be traced to project records, and asset issues have named owners.

Important: Project Twin floor metrics and parts of the model/telemetry are illustrative. Sensor thresholds are browser-local. These are not a verified real-time digital twin until actual models, asset IDs and feeds are integrated.

21

5 · Finance (ERP)

Commercial core — BOQ revisions, variations and verified payment

Responsible: Commercial manager and contract administrator

  1. 1

    Configure the contract

    Open Commercial Controls → Contracts, valuation & payment applications → Contracts & SOV. Configure contract framework, native currency, original value, retention, advance recovery and VAT. Original value is not a manually entered revised contract total.

  2. 2

    Import or author BOQ/SOV

    Choose Import BOQ / SOV. Upload CSV or XLSX, choose worksheet, map code/description/unit/quantity/rate and optional activity columns, inspect preview and validation, enter import reference and effective date, then Save. Imports are limited to 1,000 rows per atomic batch; errors save nothing. Use New for manual entry or Promote approved estimate. Units include m3, kg and No.; duplicates are rejected case-insensitively.

  3. 3

    Define visual valuation stages

    Open Edit on a draft BOQ. Choose Measured (one 100% stage), Lump Sum (ls, quantity 1), or Milestone. Name stages and allocate exactly 100%, selecting inspection, document evidence and partial completion rules. Approve with a reference. Each stage values verified physical quantity divided by contract quantity, multiplied by its allocated item value; measured work uses 100%. Nonpartial stages require the full quantity.

  4. 4

    Control effective revisions

    Choose Controlled revision on an approved unmeasured BOQ. Enter effective date and approval reference. Revision history retains immutable before/after snapshots. Once a measurement exists, rates, quantities and stage rules cannot be overwritten; use a separately authorized variation item. Existing IPC snapshots are never repriced.

  5. 5

    Create joint measurements

    Open Measurement → New. Select approved BOQ; unit/rate and previous verified/current/cumulative stage quantities appear. Select a named stage, method, dimensions/count, date/location, multiple supporting documents and inspection evidence. Save, Submit with reference, then Record consultant / QS verification. Duplicate references and quantities beyond the stage contract limit fail. Evidence locks on submission. Previous quantities are stage-specific, not summed across unrelated milestones.

  6. 6

    Authorize one variation pipeline

    Open Variations. Log change event, then New variation proposal (FIDIC), Compensation event (NEC) or Change order (AIA). Enter itemized prices without automatic markup, effective date and time impact; optionally link a legacy construction change and proposed durations for unstarted activities. Review cost/time, then employer Authorize BOQ: approved BOQ lines and contract revision are created together once. Revised contract value derives from original plus authorized owner changes. Legacy records remain history; they are not automatically rebilled.

  7. 7

    Apply schedule handoff separately

    Inspect the proposal schedule_impacts in record details, comparing source activity timestamp and proposed duration. After authorization use Apply schedule preview with a reference. Only unchanged, unstarted Task Dependent activities may apply through the existing scheduler save guard. Stale work requires a new reviewed proposal. Baselines do not move; recalculate CPM in P6 after handoff.

  8. 8

    Create, certify and authorize payment

    Payment Applications → New creates a draft from unbilled verified measurements within the period. Submit, consultant certify with evidence, then employer authorize and post AR. Required inspections and unresolved critical NCRs hold certification. Fiscal controls, retention/advance caps, native currency and balanced journal posting remain enforced. ERP records receipts; DPRs are not payment entitlement. Template selection remains a presentation choice, not a certified contract form export.

Done when

Reload the imported/revised BOQ, inspect stage-specific measurement and variation history, and trace authorized IPC to its single AR invoice.

Important: Separate hosted consultant/client accounts, external ERP activation and licensed certificate forms are not certified by this release. New construction variations are owned by Commercial; historical construction changes remain read-only.

22

4 · Construction Site → 5 · Finance (ERP)

Legacy daily quantities to IPC — historical supervised exercise

Responsible: Quantity surveyor, site manager and finance controller

  1. 1

    Save an incomplete DPR as a draft

    Save DPR draft works before any quantity lines are entered: date, weather, labor, narrative and delays are kept, and you can reopen the draft later to add quantities. Approve quantities stays disabled until at least one quantity line is saved.

  2. 2

    Prepare actual quantity evidence

    Obtain an authorized real BOQ and its matching dimensioned drawing, with revision, sheet and scope. Calibrate one known dimension and check another independently. For mixed-scale sets calibrate each page separately. Measure a known area, change zoom, save/reopen and compare with like-for-like BOQ scope and units. A BOQ total alone cannot validate drawing scale. Phase 6 synthetic test measured a 10m × 6m rectangle as 60m2 and a 32m perimeter, preserved after reload; it does not establish real project accuracy.

  3. 3

    Practice DPR approval without changing live work

    Use a separately designated training project, not a production project or the locked Live Demo. A 100m2 quantity plan at SAR25/m2 with a 40m2 approved DPR produces 40% completion and 60m2 remaining. A draft must not affect schedule progress. A later approved report that takes cumulative quantity over 100m2 must fail. Open Projects → Construction Site and the schedule to verify source records and 40% progress.

  4. 4

    Practice the complete billing chain

    For those 40m2, claim SAR1,000, certify SAR900 with 10% retention (SAR90), and clear SAR810. Record explicitly labeled test receipts of SAR300 and SAR510 only within the isolated training project. The first leaves SAR510 net outstanding; the second settles the SAR810 AR invoice. Verify separate claimed/certified/cleared/received totals, original quantity lines, bank references, dates and balanced journals, then remove test records under the agreed data-management process. Never use this example to claim an actual client certification or bank receipt. Before submission save CLAIM-TEST as the claim backup reference. After submission, record CLIENT-TEST as client approval, then certify. For 100 m2 at SAR 25, approve 40 m2: previous 0, current 40, cumulative 40, claimed SAR 1,000; certify SAR 900, retain SAR 90, clear SAR 810 and receive SAR 300 + SAR 510.

  5. 5

    Review controls and limits

    Only administrators and project directors configure quantity plans and save/approve DPRs. Client IPC actions require finance or management; vendors cannot read internal quantities or IPCs. Approved reports and certified invoices are locked, stale revisions rejected, and closed projects cannot receive new workflow actions. The one-time billing reservation prevents overlapping claims. This release is not statutory certification, tax determination, retention release, offline DPR approval or external bank integration.

Done when

Saved quantities, schedule %, IPC stages, canonical AR balance and one balanced journal per transaction reconcile. Real drawing/BOQ comparison remains pending until supplied.

Important: Live Demo navigation and its existing training records are unchanged. This chapter provides the Phase 6 exercise without adding another wizard. This is the retained legacy exercise, not the source for new contractual claims; use Contractual Commercial Controls for contract BOQ and jointly verified measurements.

23

5 · Finance (ERP)

Match invoices and settle AP/AR

Responsible: Accounts payable/receivable and finance approver

  1. 1

    Capture and check the invoice

    Use Document AI to extract supplier invoice fields when available. Compare every extracted amount, tax, date, vendor and PO reference with the original invoice before creating or approving the financial record.

  2. 2

    Run the three-way check

    Compare PO quantities/prices, accepted goods receipt and supplier invoice. Investigate quantity, price or tax mismatches and compliance holds; document the resolution rather than forcing a match.

  3. 3

    Approve and record settlement

    An authorized user approves the invoice and records the actual payment with its date, amount and reference. For client AR, check the issued invoice and record actual receipts. Reopen each invoice to confirm balance and status.

  4. 4

    Inspect the ledger trail

    In ERP, open the related journal and account ledger. Trace entries back to the invoice/payment and confirm total debits equal total credits. Follow the settle stage in RFQ Workflow for its linked transaction.

Done when

The invoice is matched, approved and linked to an evidenced payment or receipt and balanced posting.

Important: Recording a payment in the platform does not transfer money through a bank. AI extraction and automatic posting outcomes must be reviewed.

24

5 · Finance (ERP)

Review balances, cash flow, aging and forecasts

Responsible: Finance controller and project manager

  1. 1

    Reconcile the trial balance

    Select the agreed reporting period. Review trial-balance accounts and open ledger details where provided. Confirm debit/credit equality and compare cash/bank balances to independently obtained bank statements.

  2. 2

    Review financial statements

    Choose Financial reporting scope: Company overall includes project-tagged and unallocated posted entries; a project includes only its posted entries. Select one currency and financial year, then inspect Profit & Loss, Balance Sheet, Cash Flow, AP / AR Aging and Trial Balance. Project budgets & ledger opens commitments and budgets separately. All ledger pages are read; unposted costs are not P&L expenses, aging is current-date, and currencies are not consolidated. Reconcile source journals before interpreting profit or using statements for statutory reporting.

  3. 3

    Manage aging and funding

    Review AP/AR aging buckets and overdue invoices. Check the 13-week cash forecast and budget versus committed versus actual. Assign actions for collections, upcoming payments and unfunded commitments.

  4. 4

    Review uncertainty, not just a single date

    Use Forecasts to inspect Monte Carlo and EVM results. Monte Carlo repeats outcomes with varied assumptions; P80 is the modeled outcome met in 80% of runs, not an 80% guarantee. Validate input assumptions and agree contingency actions.

  5. 5

    Run the ledger per legal entity

    Open Enterprise Ops → Multi-Entity / IC. Finance or admin users add each legal entity (code, legal name, currency, country) and assign projects to it; invoices and journals belong to their project's entity unless an invoice is overridden. Use the Entity filter to see one company or the consolidated group: AR and AP aging (current, 1–30, 31–60, 61+ days), the trial balance per entity with a balanced / out-of-balance flag, and inter-company eliminations. To mark an inter-company invoice, choose its counterparty entity; the seller's AR is matched to the buyer's AP, the matched amount is eliminated on consolidation and any mismatch is shown in red for reconciliation. This is an operational ledger, not a certified statutory one: FX translation of balances and local statutory filings remain in the corporate ERP.

  6. 6

    Currency inheritance and immutable history

    Commercial controls default to project base currency. Empty, uncommitted contract configuration follows subsequent project currency changes. BOQ/IPC and transaction currency snapshots are preserved once used; changing project settings never relabels booked money.

Done when

Balances reconcile, overdue items have owners, and forecast assumptions and actions are documented.

Important: Illustrative or incomplete inputs produce unreliable forecasts. A balanced trial balance does not prove every transaction is correct or complete.

25

5 · Finance (ERP)

FX revaluation and Saudi e-invoicing

Responsible: Finance

  1. 1

    Book a dated transaction conversion

    Open FX Revaluation & ZATCA, select the project and an unposted PO or invoice. Enter project base currency per one native currency unit, a nonfuture rate date and bank/agreed rate reference. Book FX conversion; reload to verify native and converted amounts. Example: USD 100 × SAR 3.75 = SAR 375. Issued POs post converted commitments; approved AP invoices post converted actuals. Native invoices, payments and journal lines retain native currency, with the booked rate carried on journal headers. Posted rates cannot be changed. Rates are explicitly entered, not automatically downloaded. This is not automatic settlement FX or a certified multi-currency statutory ledger.

  2. 2

    Revalue open balances

    Edit rates to SAR, review gains/losses on unpaid foreign-currency invoices and post to the ledger. SAR revaluation uses each approved/open invoice’s own booked SAR rate, not its vendor currency or a shared historical rate. Non-SAR base-currency revaluation is not included.

  3. 3

    Issue e-invoices

    Generate the numbered, chained e-invoice file. Live submission to ZATCA requires your production certificate.

Done when

Important:

26

6 · FF&E Fit-Out

Build specifications and the room-by-room FF&E scope

Responsible: Designer and FF&E manager

  1. 1

    Create or import the item list

    In FF&E Catalog, use the available item form, wizard or CSV import. Enter room, room type, item name, quantity, specification and unit cost. Replace any prefilled demonstration values.

  2. 2

    Approve master specifications

    Use Spec Library to review the product specification and any variants/project instances. Check manufacturer, model, dimensions, materials, finishes and supporting product evidence.

  3. 3

    Review the room matrix

    Open FF&E Pro and inspect rooms against item types. Resolve missing, duplicate or over-specified items. Match the quantities to the approved room list and takeoff.

  4. 4

    Control specification changes

    Before changing an approved specification, review the available impact report for affected RFQs and POs. Notify procurement and obtain approval before changing a committed scope. Follow the six-phase workflow as the scope progresses.

  5. 5

    Prepare client presentations and item tear sheets

    In Fit-Out & FF&E Management, scroll to FF&E Delivery Controls. Publish specification PDF retains the existing register export. Choose Client room presentation or Item tear sheets and press Download presentation PDF for a dedicated review copy with project/item references, quantities, specifications, manufacturers, warranties, certificates and recorded finish/evidence references. These PDFs use canonical project records and do not embed product photos or original private cut sheets. Review originals separately in the CDE and route formal specification decisions through stakeholder approvals; downloading never approves or changes scope. Custody Pipeline, Finish Samples and Room Readiness remain the working delivery tabs. An item detail's Create RFQ creates a project-linked Draft and opens the RFQ workflow for supplier invitations; it does not fabricate offers or mark an unsent request as Sent.

  6. 6

    Attach item originals and export review packages

    FF&E → Delivery Controls → Item Originals: choose a canonical item, upload private photos or cut sheets using existing document authority, or retain an external reference link. Uploaded records use explicit same-project item links. Re-export Client room presentation or Item tear sheets to include accessible PNG/JPG/WebP photos (four per item, up to 10 MB each). Download originals ZIP packages private uploaded originals (25 MB/file, 100 MB total), with a manifest listing missing or inaccessible evidence. External URLs are not fetched. Downloads are review copies, not approvals; unavailable source evidence must be supplied. Shared project material masters remain browser-local.

Done when

Each room has a reviewed quantity and approved specification, and procurement has the current scope.

Important: A heatmap is only as accurate as the underlying quantities and status updates. AI flags support review; they do not approve a specification.

27

6 · FF&E Fit-Out

Track shipment and receive goods

Responsible: Logistics coordinator and receiving inspector

  1. 1

    Validate the shipment record

    Find the shipment linked to the PO. Check carrier, route, container/reference, promised dates and delivery location against vendor documents. Record evidence for dispatch and each status update.

  2. 2

    Monitor ETA and exceptions

    Use the shipment tracker and SCM Pro to review ETA risk, customs issues and demurrage exposure. Use Advance only when the real milestone occurred, not to make the demonstration look complete.

  3. 3

    Inspect the physical delivery

    Count delivered, accepted, damaged and rejected units against the PO. Record discrepancies, photographs and inspection evidence. Do not mark ordered quantities as received without a physical check.

  4. 4

    Post and verify the goods receipt

    Use the available receive-goods workflow for the correct PO and warehouse. Reopen the goods receipt and verify accepted quantities, remaining open quantities and the corresponding FF&E/inventory status.

  5. 5

    Save a draft order with its delivery destination

    Supply Chain → Issue PO accepts a receiving warehouse, project delivery location and manual delivery address. Save draft keeps the order editable; reopen the order, change its receiving fields and Save. Issue PO and the PO Wizard capture the destination at creation, and RFQ-to-PO handoff also preserves it. Destination edits are permitted only while the order is Draft, enforced even for direct requests. A freeform address does not replace the warehouse required when posting stock receipts.

Done when

The goods receipt reconciles the PO to actual accepted delivery and documents every discrepancy.

Important: Shipment movement and ETA may be manually maintained or simulated unless a real carrier connection has been configured and tested.

28

6 · FF&E Fit-Out

Release rooms for FF&E and hand them over

Responsible: FF&E manager and site manager

  1. 1

    Confirm finishes are ready

    Each room starts at Finishes Ready. Check the FF&E installed count beside it.

  2. 2

    Advance room by room

    Press the next stage: Released for FF&E → Delivered & Staged → Installed → Inspected & Handed Over. Stages cannot be skipped.

Done when

Every room shows Inspected & Handed Over.

Important: Rooms appear automatically from the FF&E catalog room names.

29

7 · Handover & GRC

Complete installation and operational handover

Responsible: Project manager, QA/QC lead and client/facilities team

  1. 1

    Verify installed and accepted scope

    Reconcile ordered, received and installed FF&E by room. Confirm installation physically and update status only after inspection. Identify shortages, substitutions and remaining commitments.

  2. 2

    Close outstanding technical work

    Resolve punch items, RFIs and submittals; complete required inspections and hold-point signatures. Keep any accepted exceptions with an owner, deadline and written client agreement.

  3. 3

    Assemble the handover package

    Collect as-built drawings, approved specifications, commissioning records, asset/serial lists, O&M manuals, warranties and training evidence in the agreed repository. Verify real model and asset links where configured.

  4. 4

    Record client acceptance

    Obtain formal acceptance outside the platform's status indicators. In Project Twin, use the milestone edit controls to record the completed handover milestone, then reopen and check it. Do not infer acceptance from a demonstration floor progress bar.

  5. 5

    Assemble the handover package

    Add assets, as-built drawings, O&M manuals, warranties and test certificates; Submit then Accept each item.

  6. 6

    Prepare the full COBie / CAFM workbook

    Open Asset Register & COBie. Complete one physical asset per installed unit, link its same-project installed FF&E source, and record installation/warranty dates and barcode. Owner delivery data supplies COBie facility fields, Contact records and optional worksheet rows. Prepare full workbook, then Download COBie XLSX. All nineteen COBie worksheets plus FF&E reconciliation and Readme are included; missing evidence and unresolved references appear on Issue. Aggregate FF&E quantities never become invented components. Approved originals must be packaged separately using relative Document paths; private URLs are omitted. Validate the workbook against the receiving CAFM template before import; the export does not connect to or certify a particular CAFM system.

  7. 7

    Run the defects liability period

    Log each defect with the responsible subcontractor and DLP end date; overdue DLP dates are highlighted.

Done when

The client has accepted the handover package and all remaining exceptions are explicitly agreed.

Important: There is no verified automatic facilities-management handoff or single project-close action. The handover package and acceptance remain controlled business evidence.

30

7 · Handover & GRC

Maintain risks, policies and sustainability evidence

Responsible: Risk, compliance and sustainability leads

  1. 1

    Review the risk register

    In GRC & Compliance, inspect the heatmap and risk records. Confirm likelihood, impact, controls, mitigation owner and due date. Link material risks to project actions and review them regularly.

  2. 2

    Review policies and third-party exposure

    In GRC Audit, use Policy Lifecycle and Third-Party Risk to inspect policy status and supplier exposure. Review Auditor Portal and Reg Horizon information as supporting views, not proof of an external audit or live regulatory feed.

  3. 3

    Validate environmental inputs

    In ESG & Sustainability, inspect embodied-carbon and supplier/spend-based values. Check quantity, emission factor, units and source evidence. Separate measured emissions from estimates.

  4. 4

    Preserve review evidence

    Keep approved risk decisions, current policies, verified supplier checks and sustainability source records in the agreed evidence repository. Use available exports and reconcile them to the project before reporting.

  5. 5

    Project assessments and deletion

    Risks, assessments and framework coverage show only the selected project. Company controls/framework definitions remain shared libraries. Admin, Project Director, GRC Officer, QA/QC Manager and HSE Officer can delete any assessment of the selected project, including completed ones, with confirmation and an atomic audit snapshot of the removed record.

Done when

Material risks and ESG figures have identifiable owners, assumptions and supporting evidence.

Important: Some audit-policy interactions and ESG inputs are demonstrations. Do not claim delivered auditor links, signed evidence packs, regulatory compliance or certified carbon accounting without independent verification.

31

7 · Handover & GRC

Review enterprise operations and client reporting

Responsible: Portfolio manager and specialist process owners

  1. 1

    Choose only relevant enterprise processes

    Inspect resource leveling, auction, carrier/3PL, intercompany and HR areas in Enterprise Ops. Assign a specialist owner and verify what saves and what remains a demonstration before entering operational data.

  2. 2

    Verify external connections

    Review Integrations and any carrier controls. Use the approved connection process for credentials and test a real record end to end. A displayed carrier, connector or connected status is not proof of a working service.

  3. 3

    Prepare the management dashboard

    Choose the relevant Custom Dashboard widgets and inspect source records. In Client / Exec Dashboards, select the intended project and sections and remove information the recipient should not see.

  4. 4

    Share cautiously and review expiry

    Where sharing is available, set an appropriate token expiry and test the link as the intended recipient. Confirm the project, sections and access boundary before sending it. Export the approved report for the project record.

Done when

Portfolio reports are checked and any external connection or shared view has been tested with the correct access.

Important: Auto Leveling is an isolated sample ten-period sandbox, not a project scheduler. Use P6 Resource Management & Leveling for canonical project resources. Reverse Auction and 3PL tabs link to existing RFQ and logistics; no live auction/carrier integration exists. Payroll & HR links to Field payroll and employee access, not statutory tax processing. Integration catalogue does not connect services or accept private credentials; authorized setup belongs in Settings.

32

Start Here

Workspace Navigation — Suites, All Tools, Pinned Ribbon

Responsible: All users

  1. 1

    Use the left rail

    The dark left rail groups the 25 everyday tools into five industry-standard suites: Command & Workspace, Design & Planning, Site & Field Ops, Commercial & Supply, and Governance & AI. Each suite collapses; the hide button in the top bar removes the rail for more working space.

  2. 2

    Find any other screen

    Every other permitted screen (FF&E specs, shipments, finance statements, ESG, admin tools and more) is under More tools at the bottom of the rail and in the All tools menu, grouped under its original lifecycle heading. Nothing was removed.

  3. 3

    Open All tools

    All tools in the top bar shows the five suites side by side with a Find a tool box, then More tools, plus Seed Demo Data.

  4. 4

    Pin tools and use Recent

    The Pinned ribbon below the top bar holds your favourite tools; press + to add, hover a pin and press × to remove. Pins are saved per account in this browser. Recent shows the last screens you opened.

  5. 5

    Project, New Record and status

    Switch the working project from the project name in the top bar. New Record opens the matching register to create a task, RFI, daily log, requisition, RFQ, meeting or note. The breadcrumb shows project › suite › tool; the bottom bar shows sync status and the platform version.

Done when

Important:

33

7 · Handover & GRC

Reconcile, archive and formally close the project

Responsible: Finance controller, project sponsor and administrator

  1. 1

    Resolve commercial balances

    Reconcile final PO commitments, goods receipts, invoices, payments, client receipts, approved changes and retainage. Close or document remaining disputes and confirm all entries belong to the correct project.

  2. 2

    Produce the final finance pack

    Review the final trial balance, P&L, balance sheet, cash flow, aging and budget-versus-actual reports. Export the available PDF/CSV reports with the period and project identified and obtain finance approval.

  3. 3

    Treat period close separately

    Inspect the Period Close area in CLM · FX · Tax · Close for the demonstrated process. Use your organization's authorized accounting close procedure for actual locks and adjustments. A period close is not the same as closing a project.

  4. 4

    Archive and obtain sponsor sign-off

    Archive approved drawings, schedules, contracts, inspection evidence and financial exports with a retention owner. Record sponsor closure approval and lessons learned. Complete the closeout checklist and advance the project to Archived; task and activity editing in the Projects workspace then becomes read-only.

  5. 5

    Tick the closeout checklist and archive

    On Projects, open the closeout checklist and tick all ten items. Only then can the project be moved to Archived; the database refuses earlier.

Done when

Handover, final finance approval, archived evidence and sponsor closure sign-off are complete.

Important: The CLM period states currently run in page memory; changing a displayed period to Locked does not enforce an accounting lock. Retain records rather than deleting them to simulate closure.

34

Reference · Platform hardening

Platform hardening: large schedules, offline field work, KSA e-invoicing and system exchange

Responsible: Planning lead, site engineers, finance controller and system administrator

  1. 1

    Check schedule capacity

    Open Platform Hardening → Scheduling scale & XER. Enter an activity count (for example 10,000 or 30,000) and press Run CPM. Schedules of 500+ activities are calculated in the background so the screen stays usable; the time and critical count are shown. The P6 screen shows the calculation time on its summary cards.

  2. 2

    Verify an XER file before relying on it

    Drop the Primavera XER into the XER fidelity check. Confirm the counts of activities, calendars, resources, assignments, constraints and actual dates. Activity user-defined fields and activity codes appear in a table: edit a user-defined field value in place (activity codes are read-only and come from the P6 code dictionary). Every other table (notebooks, expenses, other codes) is kept verbatim, and links inside those tables are re-pointed to the activity and WBS codes so they still match after re-import. Download the round-trip XER and import it into Primavera to confirm.

  3. 3

    Work offline on site

    Enter timecards, equipment and supported punch items as normal. Meeting drafts, actions, review and finalization require a connection. Without signal they are stored in the device database. Open Offline field sync to see waiting records; they send in order when online and retry automatically. Records marked 'conflict' (duplicate or not permitted) need you to Retry or Discard.

  4. 4

    Prepare KSA e-invoices

    In KSA ZATCA & VAT enter the seller's legal name and 15-digit VAT number (starts and ends with 3). Every invoice is shown in SAR with the declared VAT compared to 15%; mismatches are flagged. Press QR to produce the ZATCA Phase 1 QR code (seller, VAT no., time, total, VAT) and its hash. Phase 2 clearance needs your ZATCA certificate and a certified provider.

  5. 5

    Exchange data with other systems

    In Integrations choose the project and export: Primavera P6 XER, a Procore RFI import CSV, or GL journals in SAP (FB50) or Oracle Fusion (GL_INTERFACE) layout. Import the files in those systems. Live two-way API sync requires each vendor's API credentials.

  6. 6

    Know the limits

    Primavera remains the tool for forensic delay claims and priority-based leveling; native apps remain stronger for weeks without signal and offline photos; statutory books, Zakat returns and audit sign-off stay in your certified finance system.

  7. 7

    Service worker safety controls

    The offline app shell registers only on the published site. It never registers in the editor preview, in iframes, or on preview hostnames, and any stale copy there is removed automatically. Appending ?sw=off to the URL unregisters the app worker immediately — use it if a published device ever serves a stuck cached copy.

  8. 8

    Use the Field screen on a phone, with or without signal

    Open Field on the phone (published app). Tap Add to Home Screen when offered — on iPhone/iPad use Share → Add to Home Screen — so Field opens like an app. Get weather records the current conditions from the phone's location (the last reading stays available offline; Copy for DPR puts it on the clipboard for the DPR weather field). Site photos: add an optional note and tap to open the camera; photos are reduced to 1920 px, tagged with time, weather and note, and saved to project Documents. Without signal, photos and new DPR drafts are kept on the phone and the bar at the top shows how many are waiting; they upload automatically when signal returns, or tap Sync now. Open Field while you still have signal so the project's quantity lines are loaded before you go offline. Editing an existing DPR, approvals and IPC need a connection. This is an installable web app, not an App Store app: the phone may pause syncing while the app is closed, so open it briefly once back in coverage.

Done when

Important:

35

Construction governance

Stakeholder Register — Contractor, Consultant & Client

Responsible: Project director and document controller

  1. 1

    Read the workflow graphic

    At the top of Stakeholder Register (Master register tab) the graphic shows 1 Contractor Submit/Raise → 2 Consultant Review/Approve → 3 Client Final approval with live pending counts; click a step to open that party portal. Below it, click Documentation (RFIs, submittals, method statements, drawings), Site inspections or Centralized log (all records) to filter the register; the active card is highlighted. Use Seed sample records (admin) on an empty project to see it populated.

  2. 2

    Choose Classic Register or Executive Cockpit

    Master register now offers Classic Register and Executive Cockpit above the existing workflow graphic. Classic Register is the default and retains the original nine-column log, counters and record actions. Executive Cockpit is optional: its party counters filter the queue, matching-record totals show overdue and revision workloads, and Enhanced table or Pipeline presents the same filtered canonical records. The table highlights the current responsible party; it is not a claim that every record follows all three parties. Pipeline groups active records by current party and Accepted, Closed or Rejected records under Completed; rejection is not approval. Search, type, status, category, party filters and permission enforcement remain shared. Open record, Comments and History use the existing controlled dialog. History in Executive Cockpit uses a chronological decision timeline with actor, time, revision, expandable remarks, attachment count and recorded company-stamp references, not qualified digital signatures. Lists retain selectable pagination. The Classic/Executive preference is saved per account in this browser; switching views never changes workflow data. Live Demo remains unchanged.

  3. 3

    Configure the project parties

    In Parties & routing, choose each existing app account, organization and Contractor, Consultant or Client party. Enable Authorize / approve only for designated reviewers. Activate/deactivate memberships without changing global app roles. Administrators and project directors retain management authority.

  4. 4

    Set the responsibility matrix

    For each document type choose whether client approval is required and whether clients may see issued correspondence. Each new workflow snapshots this configuration; changing the matrix does not reroute already-issued records. Contractor types include RFI, material submittal, shop drawing, method statement, technical proposal, correspondence and inspection. Consultant types include NCR, site instruction and official letter. PMP/PEP uses a canonical submittal, originated by the Contractor. Configure client-required approval before creating a new review; existing route snapshots do not change.

  5. 5

    Create and internally authorize

    + Raise Submittal / Inspection creates a canonical RFI, submittal, inspection, NCR or transmittal/correspondence record plus its routing metadata, with an automatically allocated project reference. Draft content is editable in the register. Submit internal review precedes Authorize & issue; only the originating party authorizer or project management can release it. Private internal records/events are not visible to other parties.

  6. 6

    Respond and decide

    Issued contractor records reach Consultant Review, then Client Review only when required. Consultant-issued records reach Contractor Response, then return to Consultant Review for acceptance. Provide decision comments and supporting same-project documents. Accept, Reject, Return for revision and Request clarification are stored with actor, organization and time. Inspection acceptance/rejection records the reviewer and inspection date. Existing private document access remains unchanged; upload evidence in Projects Documents using permitted document roles.

  7. 7

    Track queues, revisions and evidence

    Search/filter the master register by type/reference/stage, use My party’s queue and review due-date overdue flags. Details shows content and immutable decision/revision history with private document content previews. Close follows acceptance; Create revision starts a new draft while preserving previous events/snapshots. Governed source records reject ordinary status/content edits outside the register. Projects Construction Site includes these workflow records. Open it directly from Projects → Stakeholder Register, project setup/design/site workflow links, Projects Documents registers, PMP card 8, or Approvals → Stakeholder Register. Project record links open the exact workflow rather than an unrelated record. All ten existing governed record types and PMP/PEP use the same register and decision history; legacy cost approvals and external client review links remain separate.

  8. 8

    Supervised training exercise

    In a non-training project, configure contractor drafter/authorizer, consultant reviewer and client approver accounts. Create an RFI; confirm consultant cannot see its draft. Submit internal review, authorize, accept as consultant, approve as client if configured, close, create revision and reload. For NCR, create as consultant, authorize, respond as contractor with corrective evidence and accept as consultant. Verify wrong-party decisions fail and history remains unchanged.

  9. 9

    PMP document-backed review exercise

    Upload an authorized PMP/PEP plan in Projects Documents. From PMP choose Export PMP status PDF and verify all twelve areas. Start PMP sign-off, select the uploaded plan and a review due date, and create the draft. Confirm its PMP reference, original attachment and fixed status snapshot; submit internally, authorize, review as consultant and client if configured, close, then reload Projects Stakeholder Register to read the same workflow and history. Do not treat the status PDF alone as a contractually approved execution plan.

  10. 10

    Use the three party portals and complete log

    Master register contains Master Log, Contractor portal, Consultant portal and Client portal views over the same records. Parties see only permitted records; portal queues show the party responsible for the next action. The nine-column log shows reference, type, title/description, raised by, current stage, named actor or party authority, status, submission date and actions. Revision and due-date details remain visible. View, Comments and History open the same controlled record; Download record creates a status/history PDF, not a digitally signed original.

  11. 11

    Assign named document authorities

    Administrators and project directors configure active project members with Initiate and Authorize/approve permissions. The per-document authority matrix can designate initiator, internal approver, consultant reviewer and client approver from eligible members of the correct party. Party authority means the existing party-level authorization applies when no individual is assigned. Assignments are snapshotted when creating the workflow; changing configuration does not silently reroute issued records. Only the designated current actor can act when assigned, except project management. Use Edit to change a saved member. Account selection and form input do not trigger record drilldowns or reset the active tab.

  12. 12

    Conduct an inspection with structured evidence

    Choose Inspection when creating a governed record, enter inspection type, location, preferred date and description and attach existing private project files or photographs. Internal authorization releases the inspection to the consultant. Details, Attachments/Photos, Checklist, Comments and History are separate panels. The consultant records workmanship, dimensions, materials, safety and specification compliance, selects a result and saves inspection evidence before deciding. Approve with comments requires remarks; Request revision returns to the originating party. Client approval follows only the snapshotted matrix. Checklist/result evidence is revision-checked and retained in history; approved records cannot be overwritten through a comment.

  13. 13

    Review notifications and approval evidence

    Notifications displays unread in-app transition alerts for eligible responsible project members. Open record marks the alert read. Reviewers may select an active company approval stamp when authorizing, approving, rejecting or closing; the immutable event records its stamp ID with signer, organization, action and timestamp. Originals remain in the project CDE and are previewed through the existing private access controls, without copying files or broadening external access. These are authenticated approval records, not qualified electronic signatures. Email and push delivery are not enabled.

Done when

Internal authorization, configured external routing and revision history are visible against the selected project.

Important: Existing legacy records are not automatically enrolled. This release has due-date flags and work queues, not scheduled email/push reminders; evidence uses existing private project-document permissions, not new external upload permissions. Recorded authenticated approvals are audit evidence, not qualified electronic signatures or a guarantee of FIDIC/legal compliance. Global staff permissions remain separate; workflow parties do not gain company-wide data access.

36

5 · Finance (ERP)

Fiscal integrity, purchasing match and bank reconciliation

Responsible: Finance controller

  1. 1

    Fiscal periods

    Create non-overlapping periods with dates and project/global scope. Lock or reopen with an audit reason. Locked dates reject journal headers/lines, posted invoices and payments, including backdated posting. This is durable period enforcement, not a complete year-end statutory close.

  2. 2

    Purchasing match

    Map each draft AP invoice line to its PO line. Check ordered quantity, cumulative approved invoice quantities, accepted/partial QC receipts, unit rate, total and currency. Resolve mismatches before approval; posted line edits are blocked. No configurable tolerance or automatic exception-resolution engine is claimed.

  3. 3

    Bank statement reconciliation

    Enter statement reference and CSV columns line_ref,transaction_date,currency,amount,description. Match a statement line to one existing payment with exact signed amount and currency. Keep unmatched entries for investigation. This is import/reconciliation, not an active bank connection.

Done when

Saved source records and supporting evidence reconcile; resolve rejected actions before proceeding.

Important: Live Demo sequence remains unchanged. External credentials, real-project evidence and certification are not fabricated.

37

6 · FF&E / 7 · GRC

FF&E custody, samples, corrective actions and permits

Responsible: Designer, QA/QC and site manager

  1. 1

    FF&E custody and readiness

    Items persist per selected project. Record sequential custody stages with condition, location and evidence reference. Installation requires room release, MEP/finishes sign-off, accepted governed inspection and no open room punch items. Record finish samples with barcode, technical document and governed approval. Publish specification PDF from current item/sample records; attached originals remain privately previewable.

  2. 2

    CAPA and permits

    Assign NCR commercial scope/severity, then root cause (5 Whys/Fishbone), corrective/preventive actions, owner and due date. Attach remediation evidence and record effectiveness verification. Register permit authority/type, dates and owner; expiry shows Expired, Expiring within 30 days or Valid. These registers do not establish ISO certification or automatic government permit renewal.

  3. 3

    Clause audit and quantitative risk

    Audit Checklist records framework, clause, criterion, owner and assessed result. Pass requires project document evidence; Fail requires a project NCR. Assessments are revision checked and audited. Quantitative Risk extends existing project risks with probability percentage, cost impact, schedule impact and automatically calculated expected cost (probability × impact / 100). Currency is the project currency; these are estimates, not guaranteed losses.

  4. 4

    Attach item originals and export review packages

    FF&E → Delivery Controls → Item Originals: choose a canonical item, upload private photos or cut sheets using existing document authority, or retain an external reference link. Uploaded records use explicit same-project item links. Re-export Client room presentation or Item tear sheets to include accessible PNG/JPG/WebP photos (four per item, up to 10 MB each). Download originals ZIP packages private uploaded originals (25 MB/file, 100 MB total), with a manifest listing missing or inaccessible evidence. External URLs are not fetched. Downloads are review copies, not approvals; unavailable source evidence must be supplied. Shared project material masters remain browser-local.

Done when

Saved source records and supporting evidence reconcile; resolve rejected actions before proceeding.

Important: Live Demo sequence remains unchanged. External credentials, real-project evidence and certification are not fabricated.

38

1 · Design & Documents / 2 · Scheduling

Tender exchange and advanced schedule analysis

Responsible: Estimator and planner

  1. 1

    Structured tender exchange

    XLSX export/import carries BOQ, estimate settings, build-ups and indirects. Review validation issues before replacing an editable draft. Supplier bid leveling reports full-line coverage and comparable totals. Unknown workbook formulas/sheets are not losslessly preserved. Large-tender database limits remain: previous 10,000-line check passed; 50,000-line insert timed out.

  2. 2

    Priorities, fragnets and equipment

    Priority 1 is highest; analysis defers lower-priority unstarted activities within float without extending finish and reports unresolved overloads. Existing Resources Apply/Discard remains the controlled write path. Fragnet analysis inserts a hypothetical delay after a selected activity, retains source calendars/activities in saved delay evidence and does not change the live plan or approved baseline. It is a planning simulation, not contractual entitlement determination. Field equipment logs include start/end hour-meter readings; inspect readings before saving.

Done when

Saved source records and supporting evidence reconcile; resolve rejected actions before proceeding.

Important: Live Demo sequence remains unchanged. External credentials, real-project evidence and certification are not fabricated.

39

Cross-module ownership

One owner per function: billing, documents, schedule, finance and closeout

Responsible: Commercial manager, document controller, planner, finance and closeout lead

  1. 1

    One payment engine

    New payment applications follow: approved contract SOV → valuation yardstick → verified measurement → application → consultant certification → employer authorization → payment. Use + New payment application: choose the certificate template (custom IPC, FIDIC, AIA G702/G703, NEC4) — templates change presentation only. The wizard shows eligible items, previous/this/cumulative claimed, retention, advance recovery and tax, and blocks a second application for an overlapping period. Site DPRs remain progress evidence, not billing entitlement. Legacy IPC/AIA records stay read-only under Reports & legacy history.

  2. 2

    Securities & guarantees

    Commercial → Securities registers performance bonds, advance payment and retention guarantees with issuer, amount, currency and expiry. Expiring items are flagged; release requires evidence and a released security can no longer be edited.

  3. 3

    Documents and approvals

    The CDE keeps drawings, specs, transmittals and stamps. RFIs, NCRs, site instructions and consultant letters are routed once through the Stakeholder Register authority matrix. Document AI extraction now belongs to Procurement (one entry point).

  4. 4

    Takeoff units and calibration

    BOQ units include kg and No. Calibration is saved per page and shows its status; Reset calibration invalidates that page's length/area values until it is recalibrated.

  5. 5

    Schedule integrity

    Earned Value shows explicit warnings when activity budgets, baseline, actual cost or progress are missing — values are never fabricated. Enterprise activity filtering sits inside EPS; resource priority leveling and delay/TIA fragnets are separate tools, and the approved baseline is never overwritten.

  6. 6

    Finance and procurement ownership

    PO · receipt · invoice matching is under Procurement; bank reconciliation is Finance → Payments & Bank; Finance → Currency, Close & Tax links to FX revaluation, period close and tax settings. The Contract Lifecycle screen now shows one owner area at a time.

  7. 7

    Closeout & handover

    Handover Asset Register prepares all nineteen COBie 2.4 worksheets plus reconciliation and delivery notes from canonical registered assets and owner delivery data. Issues identify missing evidence; full worksheet structure is not CAFM acceptance certification. Private originals remain separate and aggregate FF&E quantities are not invented serialized tags. Final Acceptance requires reviewed closeout evidence.

Done when

A new payment application traces to verified measurements; no overlapping period exists; COBie report and final-acceptance checks are reviewed before handover.

Important: Certificate templates, COBie profiles and reference standards are guidance, not certification. Securities access is role-based (finance, project director, admin).

40

Reporting & sustainability

Custom reports, report templates and procurement-based ESG

Responsible: Project director, planner, procurement lead, sustainability lead

  1. 1

    Add a report from a template

    Open My Dashboard & Reports → Report templates and pick one (e.g. Commercial & billing summary). Its charts and tables are added for the selected project; open the gear on any widget to change it.

  2. 2

    Build your own chart or tabular report

    Add Widget → Custom Data Widget, then the gear: choose a data source (or type any table name and press Enter), a view (bar, horizontal bar, stacked, line, area, pie, donut, radar, scatter, gauge, table, tabular report with totals, pivot), group/series/value fields, metric (count/sum/average), filters, a date range and whether to show only the selected project. Click any bar, slice or row to drill into the records.

  3. 3

    Export an estimate to PDF

    In Estimating, save the estimate and click Export PDF. The document contains the summary (direct, indirect, markup, contingency, total and cost-type split), totals by CSI section, every line with quantity, unit rate, build-up and amount, and indirect costs. Estimates not yet approved are marked NOT APPROVED.

  4. 4

    Daily reports and site photos

    DPR numbers count calendar days from the project start date in Project Setup (start date = DPR-001). Site photos have View, Download and Delete; deletion is refused if your role cannot remove project documents. All labour and equipment costs show in the project currency.

  5. 5

    ESG from procurement

    ESG & Sustainability reads the selected project's PO lines, goods receipts, FF&E items and supplier ESG data. Each line is counted once: linked FF&E specification factor, else quantity × material factor when units match, else spend × supplier intensity, else a documented spend factor. Committed uses ordered quantity; actual uses received/accepted quantity. Add EPD or supplier factors in Emission factor library; they override built-in references. Lines with fallback factors and suppliers without assessments are flagged; figures are zero only when no relevant records exist.

Done when

Important:

41

AI execution and discipline review

Executable AI actions across every module

Responsible: Discipline reviewers and product owner

  1. 1

    Private project-wide Copilot conversations

    Open AI Copilot and select New conversation. Each conversation has its own page and private account-saved history. Choose a project or ask about any project your account can access. Copilot reads authorized live evidence, shows tool activity and cites records; follow-up questions retain the conversation context. Stop cancels generation. Rename or delete conversations in the list, or copy/download the transcript. Specialist tools & prompt library remain available on the Copilot home page. AI credits apply; answers do not approve, send or post operational changes.

  2. 2

    Run real project-aware AI

    Sign in, choose the intended project and open AI Actions in any module header. Select an analysis or drafting action, review the loaded source evidence, add notes or a PNG/JPG/WebP source image up to 4 MB, then select Run Analysis. Generation uses AI credits and streams the actual result. Stop cancels the active request and keeps partial output. Review the verdict, cited findings, editable draft fields and missing evidence. Copy or download the result; Review follow-up task opens an editable task with title, priority and due date. Confirm & save task creates one canonical project task only with backend authority and an open project. Existing drawing, schedule, purchasing, approval and accounting engines are unchanged. Credit or access blocks pause new calls; an administrator confirms restored access with Resume after access restoration, then the presenter starts a fresh request. Clearing a pause never retries earlier work automatically.

  3. 3

    Projects & PMP

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Live lifecycle records, task management and PMP area summaries; global Copilot can help draft tasks and notes. Broader expansion target (not all sub-capabilities automated): Project brief → proposed WBS, responsibility map and stage-gate checklist; explain incomplete evidence across the lifecycle. Source evidence: Project brief, project type, location hierarchy, tasks, PMP snapshots and stage evidence. Review output: Reviewable setup checklist with linked evidence and proposed owners; never an automatic project sign-off. Reviewer: Project director. Handoff: Approved scope informs Design, Estimating and Scheduling. Acceptance: Compare suggested scope and missing gates against a director-reviewed project; measure missed obligations and false alerts.

  4. 4

    Design, CDE & Drawings

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Private originals, drawing revisions, document previews and governed stakeholder reviews; automatic cross-document specification validation is not complete. Broader expansion target (not all sub-capabilities automated): Title-block extraction, revision-change summaries, specification conflicts and RFI drafting with page citations. Source evidence: Authorized drawing/spec originals, revision metadata, review decisions and document standards. Review output: Proposed metadata and conflict list citing file, revision and page; reviewer decides registration and RFI issue. Reviewer: Document controller and designer. Handoff: Accepted drawing revision supplies Takeoff and site document control. Acceptance: Benchmark title-block fields and conflict recall on independently reviewed drawings; reject unsupported citations.

  5. 5

    Takeoff & Measure

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Calibrated 2D length, area, count and derived volume; no autonomous validated BIM-to-BOQ engine. Broader expansion target (not all sub-capabilities automated): Suggest measurement regions and BOQ classifications; flag missing scale, depth, duplicate scope and unit mismatches. Source evidence: Published drawing revision, page calibration, saved measurements, units and explicit depth/height. Review output: Suggested measurements and exception list; deterministic geometry remains the quantity authority. Reviewer: Quantity surveyor. Handoff: Reviewed quantities snapshot into Estimating. Acceptance: Check quantities against QS ground truth per unit, including m³; no invented hidden dimensions.

  6. 6

    Estimating & Cost Planning

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Historical-rate retrieval, crew build-ups, quote evidence, escalation and controlled baselines are implemented rule-based tools. Broader expansion target (not all sub-capabilities automated): Natural-language rate lookup, omitted-scope detection, abnormal rate warnings and tender qualification drafts. Source evidence: Accessible historical estimates, units, currency, dated quotes, productivity and current line build-ups. Review output: Suggested rate with source/date/currency and explained exceptions; no silent repricing of approved content. Reviewer: Estimator / commercial lead. Handoff: Approved estimate → budget baseline, procurement packages and contract BOQ. Acceptance: Back-test quote coverage, unit/currency matching and abnormal-rate precision on reviewed tenders.

  7. 7

    BIM Coordination

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: IFC import, bounded mesh clash checks and canonical RFI evidence; geometry/session storage and live Autodesk access remain limited. Broader expansion target (not all sub-capabilities automated): Group clashes by root cause, suggest responsible discipline and draft coordination RFIs with source IDs. Source evidence: IFC fingerprint/GlobalIds, deterministic clash result, source coordinates and applicable specifications. Review output: Reviewable clash groups and RFI draft; AI does not declare geometric collision or certify model completeness. Reviewer: BIM coordinator. Handoff: Confirmed clash → canonical RFI → approved design response. Acceptance: Measure grouping quality and citation validity on coordinator-labelled IFC cases; preserve the geometry verdict.

  8. 8

    Scheduling & Calendars

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Calendar CPM, baselines, leveling, TIA and health checks use deterministic engines; selected AI schedule commentary is available. Broader expansion target (not all sub-capabilities automated): Explain schedule health exceptions, draft delay narratives and compare mitigation options. Source evidence: Activity logic, resources, calendars, baseline, data date, risk links and saved TIA evidence. Review output: Cited schedule-health narrative and what-if recommendations; date changes remain previewed and formally applied. Reviewer: Planning lead. Handoff: Approved programme informs Procurement, Field progress and commercial delay review. Acceptance: Reconcile every reported date/float with the engine; assess narrative evidence and no unsupported entitlement.

  9. 9

    Procurement, RFQs & Requisitions

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Canonical RFQ offers, bid comparison, controlled awards and requisition-to-PO handoff; no live reverse auction. Broader expansion target (not all sub-capabilities automated): Extract supplier quotes, normalize exclusions, compare like-for-like scope and explain bid risks. Source evidence: Supplier originals, RFQ lines, quote currency, delivery lead time, exclusions and documented ratings. Review output: Editable comparison with source citations and missing criteria, not an automatic winning bidder. Reviewer: Procurement lead. Handoff: Authorized award → PO → receipt/QC → matched AP and ledger. Acceptance: Verify quantities, currencies and exclusions against originals; benchmark missing-scope detection and reviewer corrections.

  10. 10

    Vendors & Vendor Portal

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Vendor profiles, accepted vendor mappings and scoped purchasing records; independent-party pilot acceptance remains pending. Broader expansion target (not all sub-capabilities automated): Summarize vendor compliance evidence, quotation questions and missing onboarding documents. Source evidence: Only the caller's permitted vendor records, submissions, insurance and accepted project mappings. Review output: Evidence-linked onboarding checklist or clarification draft; never expose other suppliers' offers. Reviewer: Procurement / vendor administrator. Handoff: Approved onboarding supplies controlled invitations and purchasing eligibility. Acceptance: Run separate-account isolation tests and compare compliance flags with procurement review.

  11. 11

    Supply Chain & Warehousing

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Recorded shipments, container/demurrage information and receipt-linked stock; live carriers and full WMS are not implemented. Broader expansion target (not all sub-capabilities automated): Explain late delivery exposure, propose consolidation and flag receipt/stock discrepancies. Source evidence: PO required dates, recorded shipment events, receipt/QC lines, warehouses and installation demand. Review output: Exception report with data freshness and proposed follow-up; no invented live ETA or stock movements. Reviewer: Logistics / warehouse lead. Handoff: Verified receipts feed FF&E custody, inventory and invoice matching. Acceptance: Back-test late-arrival alerts on recorded history; reconcile stock recommendations to receipt evidence.

  12. 12

    Field, Labor, Equipment & Payroll

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Offline DPR capture, crew-shift quantities, approved timecards and controlled payroll; selected AI daily-report drafting exists. Broader expansion target (not all sub-capabilities automated): Voice/photo-assisted DPR drafts, productivity exceptions and wage/timecard anomaly explanations. Source evidence: Authorized transcripts/photos, crew shifts, quantities, approved wage rates and timecard evidence. Review output: Editable daily report and exceptions; supervisor approves progress and finance approves payroll. Reviewer: Site engineer / payroll controller. Handoff: Approved DPR → schedule progress; approved payroll → balanced ledger. Acceptance: Check extracted quantities/hours against source notes; measure correction rate; never infer wages or tax obligations.

  13. 13

    Construction, RFIs & Submittals

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Canonical RFIs, stakeholder review gates, submittals, punch evidence and immutable decisions. Broader expansion target (not all sub-capabilities automated): Draft RFI responses, summarize review comments and prioritize overdue decisions by construction impact. Source evidence: Permitted original documents, questions, decisions, linked schedule activities and SLA dates. Review output: Cited response and decision-risk summary; signatures and approvals remain with the authorized parties. Reviewer: Resident engineer / consultant. Handoff: Issued decision informs drawings, site work and commercial change review. Acceptance: Review answer factuality and citations; verify internal comments never reach external parties.

  14. 14

    Quality, Inspections & Hold Points

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Inspection templates, NCR/CAPA records and evidence-based witness gates. Broader expansion target (not all sub-capabilities automated): Suggest inspection checklists, group recurring defects and draft root-cause/CAPA proposals. Source evidence: Specification clauses, inspection results, NCR photos, corrective actions and witness evidence. Review output: Review checklist and cited defect trend; AI cannot release an unsigned hold point. Reviewer: QA/QC manager. Handoff: Verified corrective action → room release and handover evidence. Acceptance: Check recurring-defect precision and completeness against QA review; preserve witness/signature gates.

  15. 15

    Safety & OSHA

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Incident records, OSHA logs and deterministic safety metrics; AI is not a certified safety inspector. Broader expansion target (not all sub-capabilities automated): Draft incident narratives, propose toolbox talks and flag missing investigation evidence. Source evidence: Reported incidents, approved method statements, risk assessments and authorized site photos. Review output: Reviewable narrative and evidence checklist; urgent safety decisions remain with qualified staff. Reviewer: HSE officer. Handoff: Approved actions inform Field planning and GRC risk controls. Acceptance: Assess false negatives with qualified HSE reviewers; never replace emergency escalation or statutory classification.

  16. 16

    Commercial & Subcontracts

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Approved BOQ, measured claims, variations, retention and controlled AR posting. Broader expansion target (not all sub-capabilities automated): Draft variation narratives, explain claim exceptions and identify missing contractual backups. Source evidence: Executed contract clauses, approved BOQ, verified measurements, notices and variation evidence. Review output: Cited review memo; no new entitlement, automatic certification or retroactive repricing. Reviewer: Commercial lead / QS. Handoff: Authorized valuation and variations → canonical finance postings. Acceptance: Reconcile claim amounts with deterministic calculations and have contractual conclusions reviewed by the commercial team.

  17. 17

    Contract Lifecycle (CLM)

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Contract register/lifecycle controls; qualified signatures and automatic legal review are not established. Broader expansion target (not all sub-capabilities automated): Clause comparison, obligation extraction, renewal summaries and risky-deviation flags. Source evidence: Authorized contract originals, revisions, approved clause playbook and obligation dates. Review output: Clause/page-cited deviation report and proposed obligations; lawyer/contract owner decides acceptance. Reviewer: Contract manager / legal reviewer. Handoff: Approved obligations feed commercial notices, procurement and calendar tasks. Acceptance: Legal-reviewed clause extraction benchmark; check missing obligations and unsupported legal advice.

  18. 18

    ERP, Financial Statements & Cash Flow

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Operational GL/AP/AR, project/company posted-ledger statements, period locks and bank CSV reconciliation; no bank execution or statutory certification. Broader expansion target (not all sub-capabilities automated): Explain P&L movement, find duplicate invoice patterns and draft close/reconciliation exception reports. Source evidence: Posted journals, authorized invoices, project/currency scope, budget and imported bank statements. Review output: Traceable variance memo and exceptions; no automatic journals, payments or cross-currency consolidation. Reviewer: Finance controller. Handoff: Reviewed exceptions return to AP/AR, budget and fiscal-close workflows. Acceptance: Reconcile each total to the posted ledger and test project/currency isolation; finance signs off material conclusions.

  19. 19

    FX Revaluation & ZATCA

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Dated FX snapshots, guarded revaluation, QR/XML preparation; Fatoora clearance requires authorized onboarding. Broader expansion target (not all sub-capabilities automated): Explain FX exposure and missing invoice/XML fields; draft reconciliation and compliance checklists. Source evidence: Open invoices, booked/reference-backed closing rates, generated XML and authoritative validation results. Review output: Exception explanation; deterministic engines calculate FX, VAT, hash chains and schema checks. Reviewer: Finance / tax controller. Handoff: Approved revaluation posts through the protected engine; clearance follows authorized ZATCA service workflow. Acceptance: Reconcile to known FX examples and official validator outputs; AI never supplies a CSID or certifies clearance.

  20. 20

    Document AI

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: AI-assisted invoice/document extraction; independent accuracy benchmark is not established. Broader expansion target (not all sub-capabilities automated): Expand extraction to supplier offers and contract fields with provenance, confidence and discrepancy review. Source evidence: Authorized originals, document MIME type, vendor/PO references and approved extraction schema. Review output: Field-level draft with source evidence and missing values; user verifies before creating operational records. Reviewer: Document controller / AP reviewer. Handoff: Verified extracted fields populate canonical procurement or finance drafts. Acceptance: Measure field accuracy on representative originals; block unsupported amounts, dates and source references.

  21. 21

    FF&E, Specs & Room Release

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Canonical items, room matrix, sample approvals, item originals and review PDFs; selected AI spec extraction available, shared material masters remain limited. Broader expansion target (not all sub-capabilities automated): Cut-sheet extraction, alternative product comparisons and room-readiness exceptions linked to procurement dependencies. Source evidence: Accessible item-linked originals, approved finishes, room requirements, PO/receipt/custody and sample decisions. Review output: Proposed specification and substitute comparison with citations; designer/client approves substitutions and room release. Reviewer: Designer / FF&E lead. Handoff: Approved items → RFQ/PO → delivery/custody → installation → asset handover. Acceptance: Compare model/dimensions/finish and unit/currency fields to originals; never substitute or release a room automatically.

  22. 22

    Handover, Assets & COBie

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Canonical asset evidence, installed FF&E links and full COBie worksheet structure; owner/CAFM acceptance still required. Broader expansion target (not all sub-capabilities automated): Find missing warranty/O&M evidence, suggest asset classifications and summarize commissioning exceptions. Source evidence: Registered assets, explicitly linked documents, installation/warranty dates and owner delivery requirements. Review output: Evidence-gap checklist and suggested mappings; no fabricated serialized assets or certified CAFM import. Reviewer: Handover manager / owner FM. Handoff: Owner-reviewed COBie and original evidence → CAFM acceptance. Acceptance: Use the owner's import template and actual CAFM test; compare required-field omissions and asset reconciliation.

  23. 23

    GRC, Audit & Policy

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Risk/control registers, framework evidence mapping, audit and CAPA; not independent ISO/SOC attestation. Broader expansion target (not all sub-capabilities automated): Suggest control-evidence mappings, risk narratives, audit exception summaries and policy changes. Source evidence: Permitted risk/control records, audit evidence, policies and authoritative framework clauses. Review output: Cited mapping and review memo; risk acceptance and attestation remain human decisions. Reviewer: GRC officer / auditor. Handoff: Reviewed actions feed CAPA, project gates and schedule-risk warnings. Acceptance: Auditor-reviewed evidence relevance and framework coverage; prevent unsupported certification claims.

  24. 24

    ESG & Sustainability

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Deterministic quantity/factor or supplier/spend carbon calculations with one method per PO line. Broader expansion target (not all sub-capabilities automated): Explain carbon hotspots, suggest lower-impact alternatives and flag weak factor evidence. Source evidence: PO quantities, FF&E specs, factor source/date, supplier intensity, receipts and verified EPDs. Review output: Traceable scenario narrative and evidence-quality warnings; calculations remain deterministic. Reviewer: Sustainability lead. Handoff: Approved alternatives return to design/procurement review, not automatic purchasing. Acceptance: Reconcile kgCO₂e to source factors and detect double counting; claims require documented verification.

  25. 25

    Dashboards, Forecasts & Project Twins

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: NLP report builder, project context Copilot, live operational KPIs and statistical forecasts; sensor twin is demonstration data. Broader expansion target (not all sub-capabilities automated): Evidence-linked executive narratives, forecast uncertainty and cross-module dependency explanations. Source evidence: Authorized project records, report definitions, baseline/data date and freshness; distinguish sample sensors. Review output: Cited narrative and scenario ranges; no invented telemetry, predictive certainty or board approval. Reviewer: Project director / analyst. Handoff: Reviewed insight → canonical task or source-module action. Acceptance: Reconcile cited metrics, measure forecast error and confirm each source's freshness and access scope.

  26. 26

    Meetings, Messages & Notes

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Controlled meeting revisions, tasks/notes and communication records; global Copilot can draft notes/tasks. Broader expansion target (not all sub-capabilities automated): Summarize permitted meetings, propose actions/owners and draft correspondence with decision references. Source evidence: Authorized transcripts/minutes, participant roles, recorded decisions and existing action items. Review output: Draft minutes/actions; meeting owner finalizes and confirms recipients before sending. Reviewer: Meeting chair / project administrator. Handoff: Accepted actions route to canonical tasks and discipline workflows. Acceptance: Compare decisions and owners with signed minutes; prevent duplicated tasks and unauthorized recipient disclosure.

  27. 27

    Administration, Connections & Hardening

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Database-validated access, module settings and authorized connection setup; catalogue entries are not active services. Broader expansion target (not all sub-capabilities automated): Explain access denials, propose least-privilege reviews and summarize sync/load-test failures. Source evidence: Redacted permission/configuration metadata, authorized audit evidence and test results; never credentials. Review output: Review recommendations and diagnostics; no automatic role grants, connection claims or secret disclosure. Reviewer: Administrator / security lead. Handoff: Approved changes use existing secured settings workflows. Acceptance: Test access recommendations with explicit permitted/denied accounts and check logs are secret-free.

  28. 28

    Documentation & Demonstrations

    Executable review/draft assistance is available through AI Actions using accessible canonical records and supplied notes/images. Available today: Shared manual, technical reference, guided training and optional presenter narration. Broader expansion target (not all sub-capabilities automated): Evidence-linked release summaries, audience-specific presentation drafts and documentation gap detection. Source evidence: Verified release records, module status, approved scripts and dated competitor evidence. Review output: Reviewable documentation/presentation drafts; never promote planned AI or sample data to delivered capability. Reviewer: Product owner / presenter. Handoff: Reviewed release documentation supports training and partner evaluation. Acceptance: Check statements against release evidence and preserve distinct stop scripts, narration choice and demo order.

Done when

Generate a cited result on permitted project records, verify the sources and only confirm reviewed follow-up tasks in an authorized open project.

Important: Two executable review/draft actions cover each of 26 module families. Original contract/spec text or clash evidence must be supplied when missing; register metadata is not an original. Up to 200 records per source are used with visible total/partial warnings. This is not whole-register certification, autonomous measurement, full DCMA-14, legal approval, CAFM acceptance or automatic finance posting. Blueprint & Rules preserves broader proposed capabilities.

42

Evaluation and preferences

Competitor coverage, enhancement priorities and color themes

Responsible: Product owner / all users

  1. 1

    Read percentages correctly

    Each score belongs to the product on its card. Full earns one point, partial one-half and gap zero, divided by all matrix rows. Equal-weight internal coverage is not market share, quality, certification or independently verified competitor parity. Planned AI receives no implementation credit; unknown vendor/edition capabilities require confirmation. Procore has scheduling/BIM/AI; Fohlio has actual Revit integration; Autodesk has a mature design/cloud ecosystem.

  2. 2

    Where we shine without overstating readiness

    ConstructiumAI connects measured scope, project schedules, FF&E purchasing, site decisions, operational finance, GRC evidence and handover. It is an orchestration layer, not a certified statutory ERP or fully connected Revit/carrier/bank platform. Read competitor briefs for their strengths, core-product boundaries, our differentiation and our remaining weaknesses.

  3. 3

    Suggested enhancements, in order

    Prioritize transactional procurement/finance and independent-party tests; durable IFC plus validated quantities; full warehouse controls/shared material masters; cited reviewed AI; authorized integrations and CAFM acceptance; representative enterprise load, security/restore and multi-currency accounting evidence.

  4. 4

    Color themes

    Open the palette icon in the top bar. Ruby, Ocean Blue, Graphite and Citrus Green extend the existing six palettes. Light/dark remains independent. The choice persists in this browser and changes semantic accents, rings, sidebar accents and charts; it does not modify business data, roles or tenant branding.

Done when

Readers distinguish internal feature coverage from readiness and proposed AI from available tools.

Important: Sources are dated directional product evidence, not a vendor-certified evaluation or a claim that all competitors lack a capability.

43

Administration & AI

AI testing directory and Welcome media

Responsible: Administrator / authorized module reviewer

  1. 1

    Test executable AI and existing specialist tools

    Docs → AI Actions & Blueprint lists all 26 module families and their two executable actions. Open the module, select the intended project, open AI Actions and review Source evidence before Run Analysis. Add original notes/image when needed. Generation uses AI credits; review cited findings and editable drafts. Existing specialist Copilot, invoice, cut-sheet and daily-report tools remain available. Confirming a reviewed follow-up task saves to Projects; generation alone changes no operational records.

  2. 2

    Upload website media as an administrator

    Use Manage Welcome Media on Welcome or Welcome Media in Settings. Upload MP4, WebM, MOV or M4V videos up to 100 MB; add JPG, PNG, WebP or GIF images up to 10 MB each. Uploading and saving states, success and errors are shown; the same file can be selected again. Use the pencil to edit a caption and optionally choose a replacement file, then Save or Cancel. Replacements preserve the current original if saving fails. Reorder with arrows or use Delete and confirm removal. Uploaded media is displayed above A complete platform, not point tools. MOV/M4V playback depends on browser codec support; MP4/WebM are preferred for website playback.

  3. 3

    Review the public presentation

    Videos have playback controls. Images cycle every five seconds with previous, next and pause/play controls. Public visitors can view published website media through temporary viewing links; only database-validated administrators can upload, edit or delete. Public storage buckets are blocked by workspace policy.

Done when

Verify saved media on Welcome and check AI outputs against source evidence.

Important: Executable AI drafts require review; broader blueprint targets are not all implemented. Welcome uploads are public website content, not confidential project originals.

44

Commercial & Finance — optional specialist services

On-Demand Consultant Services — commercial loop & protected drafts

Responsible: Project owner/director, commercial lead, finance and assigned consultant

  1. 1

    Agree the SOW

    SOW Creator provides Planning/TIA, QS/Takeoff, BIM, Claims and ESG templates. Choose an open project, consultant account, existing vendor/payee and same-project budget cost code. Agree scope, deliverables, fixed milestone fee or T&M total cap, hourly rate, currency, payment terms and milestone due dates. Issue and activate the SOW; issued commercial terms are locked. Download SOW PDF includes contract particulars and signature placeholders; it is a review copy, not electronic signing.

  2. 2

    Back up deliverable originals

    In Milestones & Escrow attach original PDFs, Word reports, draft XERs, IFC models or other evidence up to 100 MB while the milestone is pending or returned. Originals are private to assigned consultants and authorized management. Document format is explicit; supported files open in the shared preview and other files download with short-lived access links. Submit the milestone with its evidence note; management accepts or returns it.

  3. 3

    Discuss milestone evidence

    In Milestones & Escrow, open Discussion beneath the relevant milestone. Assigned consultants and authorized management send questions and clarifications during an active engagement, including while submitted or approved, until release. Reply quotes the original message; optional deliverable references are restricted to the same milestone and open private content previews. Names, party attribution and timestamps are verified by the database. Messages cannot be edited or deleted: correct a statement with a new reply. The visible discussion refreshes every ten seconds; use Refresh or Older/Newer pages for history. Released milestones and inactive engagements are read-only. Conversation evidence remains attached to the milestone and its AP bill; messages never sign off work, change fees or overwrite baselines. No public marketplace, external messaging or email/push delivery is implied.

  4. 4

    Review deliverable pre-audit

    Milestone submission automatically retains private file metadata, milestone timecards and engagement-level protected schedule/quantity branches. Deliverable pre-audit flags missing originals, unsigned hours, cap issues, schedule cycles/scope boundaries, invalid quantities and changed units. Confirm shared branches belong to this milestone. Management can generate an optional evidence-cited AI acceptance brief using credits; checks remain available without AI. Resubmissions retain separate snapshots, and released history is locked. Existing submissions are not backfilled. Uploaded content, mandatory attachment coverage, drawing scale/revision, negative float and constraint dates require specialist review: no full-project CPM or document-content certification is inferred. The pre-audit never signs off work, changes live baselines or releases money.

  5. 5

    Log and approve time

    For T&M engagements, Timesheets records milestone, work date, hours and description. The backend snapshots the locked SOW hourly rate, enforces daily hours of at most 24 across non-rejected entries, and checks both milestone and engagement caps. Weekly summaries and line reviews retain source evidence. Management approves or returns hours before milestone sign-off; reviewed entries are locked. Rejected hours do not consume the cap.

  6. 6

    Work in protected P6 and BOQ drafts

    In P6 & BOQ Drafts, management explicitly selects source activity IDs or takeoff-estimate IDs belonging to the engagement project. The backend copies only scheduling fields or quantities/units, omitting margins, buy-out rates and actual financials. Consultants edit names/durations or quantities/units in an isolated revision-checked draft. Open P6 draft or Open Takeoff draft enters the same protected branch view before any operational editor mounts. Submit for original-snapshot vs proposed-value comparison; management accepts or returns with review evidence. Export JSON retains source references, revision and changes. No action in this draft flow changes live activities, baselines or approved estimates; owners apply accepted proposals through existing native controls.

  7. 7

    Authorize release and settle through ERP

    Record funding on the engagement, sign off a submitted milestone and choose Release escrow & post AP. The database serializes releases and enforces funding coverage. One approved canonical AP bill is created atomically with debit 6100 Professional Fees, credit 2000 Accounts Payable and selected project budget actuals. Fixed fees bill the milestone amount; T&M bills approved hours only, while recorded funding conservatively reserves the full milestone cap. Repeated release cannot post again. SOW, project and budget currency must match; tax is zero in this service release and foreign-currency service billing requires further controlled work. Fiscal locks and vendor compliance holds still apply. Finance pays via ERP; released means payment authorization, not bank-paid.

  8. 8

    Stakeholders, authority and limits

    Database-validated admin, project director, commercial lead and finance manage SOWs, review time/drafts and release funds. Assigned consultant accounts see only their engagement records, shared source snapshots and private originals. No new global operational rights are granted. Existing stakeholder consultant roles are separate from this assignment. This is not a public consultant directory, KYC service, regulated escrow, tax engine, certified e-signature, full branch Gantt/XER engine or parallel drawing-measurement canvas. Automatic baseline merge is intentionally absent.

Done when

Owner can review originals, source changes and approved hours, read one AP/journal posting in ERP and pay it using the existing workflow, while operational schedules and baselines remain unchanged.

Important: Funding records do not prove bank custody. Acceptance of draft work never overwrites live baselines. Use separate assigned consultant accounts; never use Test as role as proof of backend isolation.

46

Procurement

Goal-driven Procurement Agent

Responsible: Administrator or Procurement Lead with AI Actions and create-RFQ permission

  1. 1

    Set a real procurement goal

    Choose the working project and open Bid Leveling → Procurement Agent. Enter an analysis or sourcing goal using your actual required items. Run agent uses AI credits. It inspects canonical FF&E/BOM specifications and existing RFQ packages, selects follow-up tools and evaluates their results; it is not a preset text-only brief.

  2. 2

    Inspect tool evidence

    The agent may calculate recorded supplier lead-day exposure against calendar-CPM activity starts (actual start takes precedence), discover approved suppliers by recorded names/categories and compare actual RFQ quotations with fixed price 50% / lead 50% weights. Missing weighted data are unranked. Evidence windows are bounded and disclosed; schedules above 5,000 activities are not partially calculated. Order-today exposure is not a confirmed delivery forecast or certified critical-path delay analysis.

  3. 3

    Review the proposal and approve explicitly

    A sourcing run may prepare one exact scope, source record references, approved supplier shortlist and nullable quote due date. No RFQ is written during investigation. Review & create draft RFQ opens a confirmation; Approve & create draft atomically saves one canonical Draft RFQ and unpriced bidder slots. Only the run owner with database-validated administrator/procurement authority and create-RFQ permission can approve. Closed projects and suppliers no longer Approved are rejected; repeated approval returns the same RFQ.

  4. 4

    Continue quotation-to-settlement in the existing workflow

    Open saved RFQ reads the created canonical request. Procurement issues it in the RFQ workflow, records real quotations, compares bids and performs controlled award, PO, receipt, invoice and settlement there. Agent approval sends no email, does not award a supplier and creates no PO, commitment or ledger posting. External automated quote solicitation is not connected.

  5. 5

    History, Stop and blocked access

    Recent runs retain goals, tool inputs/results, summary, proposals and approval/rejection state per owner and project. Stop cancels the active AI request and leaves no approvable unfinished proposal. Credit/access failures stop the run, retain the safe error and share the AI Actions service pause; no automatic retries occur. This is on-demand goal-driven execution, not scheduled or event-driven background monitoring.

Done when

A real approved proposal opens its saved Draft RFQ with the reviewed scope and unpriced vendor rows. Existing records and baselines remain unchanged.

Important: AI findings require commercial review; suppliers are matched by recorded categories, not verified capacity. No live emails, invented quotes, background sentinel or autonomous award is claimed.

47

Planning

Planning Agents — Auto Schedule and Space Takeoff

Responsible: Planner (schedule) and Estimator (takeoff) with schedule/estimate edit rights

  1. 1

    Generate the schedule from the BOQ (Auto Schedule step 1: Setup & BOQ)

    Open Planning Agents → Auto Schedule; step 1 is Setup & BOQ (steps: 1 Setup & BOQ, 2 Trades & Crews, 3 Drawing Locations, 4 Calendar, 5 Schedule & Validation). Enter the start date and activity prefix, then upload a BOQ (XLSX/CSV), paste rows (download the BOQ template: code,description,quantity,unit,zone) or press Use latest project estimate. Press Generate schedule from BOQ: trades and crews are matched from each description and unit, WBS groups follow the locations, one activity is created per BOQ row, and finish-to-start logic follows the standard sequence earthworks → foundations → columns → slabs → masonry → waterproofing → MEP → finishes → external works, with structure climbing zone by zone. Durations are ceil(quantity ÷ daily crew output). You land on step 5 with CPM, Gantt and labour histogram; adjust crews, locations or calendar in steps 2–4 and re-run. The Advanced section shows the derived activity logic for optional edits. Nothing enters the programme until you approve, and approval only appends a new branch.

  2. 2

    Optional: import BOQ or method statement (Advanced in step 1)

    In step 1 open Advanced to import XLSX/CSV with code, description, quantity, unit and zone/location, paste manual rows, or use the latest project estimate. Inputs are unsaved sample values until replaced. No schedule writes occur during generation.

  3. 3

    2. Define actual trade and crew productivity

    Trades & Crews accepts a matching quantity unit, output per crew/day, person/day, crew/hour or person/hour, people per crew, available crews and crew composition. Daily output = productivity × crews × people for person rates × calendar hours for hourly rates. Duration = ceiling(quantity × work fraction ÷ daily output). Different BOQ units require separate matching trade rates; no unit-mixing or assumed conversions.

  4. 4

    3. Review drawing locations

    Upload a text-layer PDF. The browser extracts page-tagged text and identifies bounded level/floor/zone/grid/building candidates. Assign the actual location to every BOQ row and confirm mapping. Scanned pages need prior OCR and this does not perform geometric quantity extraction from 2D drawings.

  5. 5

    4. Approve methodology and relationships

    Upload PDF/DOCX/TXT methodology as reference evidence. Define each practical activity with its source BOQ code, trade, work fraction, explicit predecessor codes, FS/SS/FF/SF relationship and working-day lag. Repeated work steps may each apply to the full source quantity. Confirm the breakdown and construction sequence; no generic trade sequence is silently imposed. Missing scope, cycles and unknown predecessors are rejected.

  6. 6

    5. Set working calendar

    Set project start, unique activity prefix, selected weekdays and hours/day. Enter public holidays/nonworking dates or import date lists. Automatic national holiday feeds are not connected; imported dates require review. Calendar-aware CPM uses this exact calendar, including holidays, rather than the fallback calendar.

  7. 7

    6. Generate, validate and approve

    Run schedule agent. Review actual date/float/critical rows, per-activity duration calculations, calendar-day Gantt and trade/day people histogram against available capacity. Long durations, parallel starts and incomplete work fractions are flagged; resource overload blocks approval. Export the full proposal as JSON. Approval atomically appends a dedicated AG-prefix WBS branch, new activities, an independent calendar and zero-priced canonical labor allocations. Duplicate prefixes/IDs are rejected. Existing programmes, actual progress, baselines and financial records are not updated or designated automatically.

  8. 8

    Space Takeoff

    Space Takeoff is unchanged: rectangular room schedules produce floor/net-wall/ceiling/skirting/opening quantities, using stated standard openings. Approval creates only an unpriced estimate. Productivity scheduling and room calculation use no AI credits.

  9. 9

    Enter rooms for Space Takeoff (structured table + AI quick-fill)

    Open the Space Takeoff tab. Add rooms with Add space (name, zone, room type, length, width, height, doors, windows, identical spaces), pick a preset to prefill typical dimensions, or use AI extract from schedule / notes to turn pasted schedules or tender text into rows. Review every row — red rows are missing dimensions; AI rows must quote matching source text. Duplicate rows for repeat floors, then Run takeoff agent and Approve to create one unpriced draft estimate. Formulas are fixed and use no AI credits.

Done when

Important:

48

Commercial, claims and technical review

Workflow Agents — IPC, Delay Notices and Specification Compliance

Responsible: Commercial management, Project Director and authorized lead consultant; AI Actions and domain permissions required

  1. 1

    Select the real project and workflow

    Open Workflow Agents and select Commercial & IPC, Variations & Claims or Submittals & Specs. Set a reporting period and enter your investigation goal. Run agent uses AI credits only on demand. Server-side tools inspect real records, perform the appropriate checks and retain evidence and one review draft. Empty sources are reported; no fictional project records are created.

  2. 2

    Commercial & IPC entitlement reconciliation

    Tools compare approved contract BOQ, authorized variations, verified measurements, prior billing and site reports. DPR percentages never become billing entitlement. Unapproved variations, unverified progress and cumulative quantities over BOQ are flagged. Previously billed measurements are excluded; each contractual stage percentage is applied. Commercial management confirms a human reference to atomically create a canonical Draft IPC. Changed revisions or new billing block stale approval. Submission, certification and financial authorization remain separate in Commercial; the agent posts no ledger.

  3. 3

    Delay-notice evidence and CPM

    The agent correlates dated DPR weather/blockers, RFI response lateness and recorded activity-linked delays with current calendar CPM and latest saved baseline. It drafts facts, possible effects, evidence gaps, reservation of rights and requested actions. Date overlap is not causality. Missing baseline float stays unknown; a saved baseline is not assumed contractually approved. Simulated extra delay is hypothetical and may already be present in current durations; no EOT entitlement, FIDIC clause or time-bar deadline is invented. Project Director review saves a Draft notice in delay_events with zero incremental impact, preserving existing schedule and delay evidence. Export remains not issued; actual notice issue/signature and contractual acceptance are outside automation.

  4. 4

    Supplier specification comparison

    Select a real project submittal and specification revision. Paste supplier data and requirements or read PDF, DOCX or TXT text extracts (10 MB, PDF up to 100 pages, 60,000 characters each). Paragraph/page citations support a requirement-by-requirement matrix of supplier evidence, numeric/unit/material comparison, non-compliance and corrective evidence. Missing claims remain Not evidenced; image-only/scanned pages require OCR. Files are read locally, and the text is retained in private investigation evidence; originals must be separately registered in CDE. An authorized lead consultant confirms the review memo with a reference, then signs formal Submittal stamps in CDE. The agent never signs a stamp or updates submittal status.

  5. 5

    Review, history, Stop and safeguards

    Recent runs retain goals, tool inputs/results, summary, source-cited drafts and reviewer references. Authorized reviewers can inspect the evidence; other staff cannot read unrelated private runs. Draft confirmation is role/permission-checked and repeat approval returns the same saved record. Exported text is marked DRAFT or HUMAN-REVIEWED DRAFT — NOT ISSUED. Stop cancels the active request, and incomplete/failed proposals cannot be approved. AI credit/access blocks are retained through the shared AI Actions pause. No background monitoring, automatic posting, official notice sending, qualified signature, original-document authenticity or legal/technical certification is claimed.

Done when

Review evidence, confirm with the required authority and read back the canonical draft or review memo; perform formal certification, notice issue or technical stamp in the existing workflow.

Important: These agents are on-demand multi-step analysis with human-reviewed draft handoffs, not autonomous engineering, contractual certification or ledger posting. Oversized source windows stop rather than silently produce partial calculations.

49

Administration

Subscription & Billing — Plans, Seats and AI Credits

Responsible: Administrator

  1. 1

    Review the current plan

    Open Subscription & Billing to see the current plan, status, seats and AI credits for the period.

  2. 2

    Compare and switch plans

    Toggle Monthly/Annual, set seats (minimums apply) and press Switch to this plan. The database checks administrator rights and minimum seats, then records a billing entry.

  3. 3

    Add AI credit packs

    Add a 1,000, 5,000 or 25,000 credit pack; the credits are added to the period balance and a billing record is kept.

Done when

The new plan shows as Current and the billing history lists the reference.

Important: No payment provider is connected: records are marked Recorded (not charged). Plans do not restrict existing screens, and AI usage is not yet metered against credits.

Operating rhythm

Daily
Review site logs, RFIs, urgent risks, shipments due and offline synchronization; assign immediate actions.
Weekly
Review schedule/critical path, room completion, procurement commitments, vendor exceptions and the cash forecast.
Monthly
Reconcile posted balances, review aging and cost variance, approve reporting, and update risk/ESG evidence.
At each gate
Obtain the named owner's approval and retain the chapter's checkpoint evidence before proceeding.

Quick glossary

FF&E
Furniture, fixtures and equipment.
RFQ / PO / GRN
Request for quotation / purchase order / goods receipt note.
AP / AR / GL
Accounts payable / accounts receivable / general ledger.
WBS / CPM / EPS
Work breakdown structure / critical path method / enterprise project structure.
RFI / OAC
Request for information / owner-architect-contractor meeting.
CO / COI
Change order / certificate of insurance.
GRC / TPRM
Governance, risk and compliance / third-party risk management.
ESG / EVM
Environmental, social and governance / earned value management.